File #: 13-1487    Version: 1
Type: Agenda Item Status: Approved
File created: 11/21/2013 In control: Board of Supervisors
On agenda: 12/17/2013 Final action: 12/17/2013
Title: Community Development Agency, Transportation Division, recommending the Board adopt Resolution 193-2013 establishing non-exclusive public utility easements on County property along Perks Court to accommodate improvements constructed during the U.S. 50/Missouri Flat Road Interchange Improvements - Phase 1B Project, CIP No. 71336. FUNDING: State Transportation Improvement Program regional grant funds and Missouri Flat Master Circulation and Funding Plan local funds (No Federal Funds).
Attachments: 1. A - Approved CRS 12-17-13.pdf, 2. B - Resolution 12/17/13.pdf, 3. C - Exhibit A 12/17/13.pdf, 4. D - Exhibit A-1 12/17/13.pdf, 5. Fully executed Resolution 193-2013.pdf
Title
Community Development Agency, Transportation Division, recommending the Board adopt Resolution 193-2013 establishing non-exclusive public utility easements on County property along Perks Court to accommodate improvements constructed during the U.S. 50/Missouri Flat Road Interchange Improvements - Phase 1B Project, CIP No. 71336.

FUNDING: State Transportation Improvement Program regional grant funds and Missouri Flat Master Circulation and Funding Plan local funds (No Federal Funds).
Body
BUDGET SUMMARY:
Total Estimated Cost…………… $500

Budgeted*………………………… $500
New Funding…………………….
Savings…………………………
Other……………………………
Total Funding Available………… $500

Change To Net County Cost…… $0
*Included in the Transportation Division’s Fiscal Year 2013-14 budget and the adopted 2013 Capital Improvement Program (CIP).

Fiscal Impact/Change to Net County Cost
The cost of this proposed action is $500. This cost is related to the abandonment of an existing easement by AT&T. Payment for this proposed action will come from the construction management budget established in the CIP for the U.S. 50/Missouri Flat Road Interchange Improvements - Phase 1B Project (Project). There are no costs related to the establishment of the new easements.

Background
In 2009, the Board of Supervisors adopted Resolution 079-2009, which established a road easement and public utility easements in advance of the construction phase of the as part of U.S. 50/Missouri Flat Road Interchange Improvements - Phase 1B Project (Project). The easements were to be located on property that was purchased by the County in order to allow for the Project’s construction phase.

Reason for Recommendation
After Resolution 079-2009 was adopted by the Board, a bicycle lane and drainage ditch were added to the Project along Perks Court. The Project then went out to bid, and during construction, changes were made to the planned locations of Perks Court and the adjacent bicycle path and drainag...