Title: Transportation Department recommending Director of said Department be authorized to accept the allocation of $9,601 and execute an Airport Improvement Program Matching Grant Agreement, upon review and approval by County Counsel, for State Airport Improvement Program Matching Grant funds for engineering, administration and construction of Phase II Replacement of Medium Intensity Runway Lighting on Runway 5-23, installation of a new Precision Approach Path Indicator on Runway 23 and the Automated Weather Observation System at the Placerville Airport. RECOMMENDED ACTION: Approve. FUNDING: State Airport Improvement Program Matching Grant Funds
Attachments: 1. Blue routing sheet 7-25-08.pdf
Title
Transportation Department recommending Director of said Department be authorized to accept the allocation of $9,601 and execute an Airport Improvement Program Matching Grant Agreement, upon review and approval by County Counsel, for State Airport Improvement Program Matching Grant funds for engineering, administration and construction of Phase II Replacement of Medium Intensity Runway Lighting on Runway 5-23, installation of a new Precision Approach Path Indicator on Runway 23 and the Automated Weather Observation System at the Placerville Airport.
RECOMMENDED ACTION: Approve.

FUNDING: State Airport Improvement Program Matching Grant Funds

Body
BUDGET SUMMARY:
Total Estimated Cost $9,601

Funding
Budgeted $9,601
New Funding $
Savings $
Other $
Total Funding Available $9,601
Change To Net County Cost $0

Fiscal Impact/Change to Net County Cost:
Total project costs are estimated at $402,370. Funding from a FAA Grant for $384,049 and funds from the Placerville Airport Enterprise Fund for $8,720 have been secured. This State Airport Improvement Program Matching Grant for $9,601 completes the funding. There is no net cost to County General Fund associated with this agenda item.

Reason for Recommendation:
On May 13, 2008, the Board approved the Plans and Specifications, and authorized the advertisement for construction bids for Phase II Replacement of Medium Intensity Runway Lighting on Runway 5-23 and Installation of a new Precision Approach Path Indicator on Runway 23 and construction of an Automated Weather Observation System at the Placerville Airport.

On June 12, 2008, the Department received five (5) bid proposals and after review selected Cindy Bales Engineering, Inc. as the low bidder.

On July 1, 2008, the Board approved a motion to authorize the Director of Transportation (Director) to execute the necessary grant applications for this project pending County Counsel's concu...