Title
Community Development Agency, Transportation Division, recommending the Board consider the following:
1) Approve and authorize the Chair to sign the Notice of Acceptance with Delta Construction Company, Inc., for the Patterson Drive and Missouri Flat Road Overlays Project, CIP 72190, Agreement 16-31119, P&C 356-C1699; and
2) Authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Community Development Agency, Transportation Division, after the one-year guarantee period.
FUNDING: Local Tribe Funds (97.4%) and El Dorado Irrigation District Reimbursement (2.6%). (No Federal Funds)
Body
DEPARTMENT RECOMMENDATION
Community Development Agency, Transportation Division (Transportation), recommending the Board consider the following:
1) Approve and authorize the Chair to sign the Notice of Acceptance with Delta Construction Company, Inc., for the Patterson Drive and Missouri Flat Road Overlays Project (Project), CIP 72190, Agreement 16-31119, P&C 356-C1699; and
2) Authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from Transportation after the one-year guarantee period.
DISCUSSION / BACKGROUND
The contract for the Patterson Drive and Missouri Flat Road Overlays Project was approved by the Board on June 28, 2016 (Item 36). The improvements were open to motorists on August 30, 2016.
Recordation of the Notice of Acceptance will start legal times for guarantees, a lien period, and return of retention monies. Recordation of the Notice of Acceptance will also start the one-year guarantee period for releasing the Payment and Performance Bonds to the Surety.
Direct Construction Cost Summary:
Original Bid Price |
$ 766,000.00 |
Contract Item Cost |
$ 730,780.14 |
Contract Change Order Cost |
$ 0.00 |
Total Direct Construction Cost |
$ 730,780.14 |
Direct Construction Budget |
$ 975,000.00 |
The costs listed are estimates. Transportation will be closing out the Project with the Contractor and finalizing costs over the coming weeks. Any significant deviations from the estimates above that exceed Transportation’s allocated authority will be brought back for the Board for review and approval in a subsequent agenda item.
ALTERNATIVES
N/A
OTHER DEPARTMENT / AGENCY INVOLVEMENT
Recorder/Clerk's Office
CAO RECOMMENDATION
Recommend approval of the Department's recommendation.
FINANCIAL IMPACT
There is no change to Net County Cost associated with this item. The anticipated direct construction cost is less than the direct construction budget established by the Board. The Project is included in the adopted 2016 Interim Capital Improvement Program and is funded by Local Tribe funds and reimbursement from El Dorado Irrigation District.
CLERK OF THE BOARD FOLLOW UP ACTIONS
1) The Clerk of the Board will obtain the Chair’s signature on one (1) original of the Notice of Acceptance.
2) The Clerk of the Board will send one (1) executed original of the Notice of Acceptance to the Recorder/Clerk’s Office for recordation within ten (10) days and forward a copy of the recorded Notice of Acceptance to John Kahling, Community Development Agency, Transportation, Headington Engineering.
3) One (1) year after the recordation of the Notice of Acceptance, Transportation will verify that all warranty work, if any, has been satisfactorily completed and will notify the Clerk of the Board in writing to release the Payment and Performance Bonds.
STRATEGIC PLAN COMPONENT
Infrastructure
CONTACT
John Kahling, Deputy Director, Engineering
Community Development Agency, Transportation Division