File #: 08-1585    Version: 1
Type: Agenda Item Status: Approved
File created: 10/8/2008 In control: Board of Supervisors
On agenda: 12/9/2008 Final action: 12/9/2008
Title: Transportation Department recommending Chairman be authorized to sign Notice of Completion with V and C Construction, Inc. for the Angora 3 Erosion Control Project (JN 95160). RECOMMENDED ACTION: Approve. FUNDING: California Tahoe Conservancy Grant Funds and Tahoe Regional Planning Agency Water Quality Mitigation Funds. The requested Board action has no associated fiscal impact.
Attachments: 1. 08-3031 NOC, 2. 08-3031 Acceptance Statement, 3. 08-3031 Attachment A.pdf, 4. 08-3031 Recorders Form.pdf, 5. 08-3031 Location Map
Title
Transportation Department recommending Chairman be authorized to sign Notice of Completion with V and C Construction, Inc. for the Angora 3 Erosion Control Project (JN 95160).
RECOMMENDED ACTION: Approve.

FUNDING: California Tahoe Conservancy Grant Funds and Tahoe Regional Planning Agency Water Quality Mitigation Funds. The requested Board action has no associated fiscal impact.
Body
BUDGET SUMMARY:
Total Estimated Cost $0.00

Funding
Budgeted $
New Funding $
Savings $
Other $
Total Funding Available $
Change To Net County Cost $0.00

Fiscal Impact/Change to Net County Cost:
There is no Fiscal Impact associated with this agenda item. There is no Net County Cost.

Reason for Recommendation:
The Contract for the Angora 3 Erosion Control Project (Project) was executed by the Board on June 17, 2008. The Project was substantially completed on October 31, 2008.

The Board actions above will start legal time frames for guarantees, a lien period, and return of retention monies. V & C Construction, Inc. acceptance of the final Contract cost is attached and summarized below:

Original Bid Price $1,460,604.78
Construction Contract Item Cost $1,259,440.11
Contract Change Orders $ 65,324.48
Final Construction Contract Cost $1,324,764.59

Major Contract Change Orders on this Project dealt with additional curb and gutter on Little Mountain Lane.

The budgeted and estimated final costs for this Project are detailed below.

Budgeted* Estimated Final Costs**
Design: $ 944,879 $1,299,963.59
Right-of-Way: $ 64,114 $ 45,392.48
Construction
Engineering & Admin.: $ 501,174 $ 354,682.73
Total Construction Cost: $2,712,507***
Construction Contract: $1,324,764.59
Construction - Other:**** $ 28,519.11
Totals: $4,222,674 $3,053,322.50
*As budgeted in the 2008 Five-Year Capital Improvement Program.