File #: 19-0346    Version:
Type: Agenda Item Status: Approved
File created: 2/26/2019 In control: Board of Supervisors
On agenda: 4/2/2019 Final action: 4/2/2019
Title: Planning and Building Department, Planning Services Division-Current Planning submitting for approval the Large Lot Final Map (TM08-1463-F) for La Cañada Subdivision, creating a total of eight large lots for financing purposes consisting of six residential lots and two lettered lots on the 143-acre property. The property, identified as Assessor’s Parcel Numbers 126-100-18 and 110-020-12, located on the west side of Salmon Falls Road, approximately 1,000 feet north of the intersection with Kaila Way, in the El Dorado Hills area, and recommending the Board approve Large Lot Final Map (TM08-1463-F) for La Cañada Subdivision. (Supervisorial District 4) (Cont. 3/19/19, Item 16) FUNDING: N/A
Attachments: 1. A - Exhibits A-D
Related files: 09-1518, 18-0352

Title

Planning and Building Department, Planning Services Division-Current Planning submitting for approval the Large Lot Final Map (TM08-1463-F) for La Cañada Subdivision, creating a total of eight  large lots for financing purposes consisting of six residential lots and two lettered lots on the 143-acre property. The property, identified as Assessor’s Parcel Numbers 126-100-18 and 110-020-12, located on the west side of Salmon Falls Road, approximately 1,000 feet north of the intersection with Kaila Way, in the El Dorado Hills area, and recommending the Board approve Large Lot Final Map (TM08-1463-F) for La Cañada Subdivision. (Supervisorial District 4)  (Cont. 3/19/19, Item 16)

  

FUNDING: N/A

Body

DISCUSSION / BACKGROUND

The Board approved La Cañada Tentative Subdivision Map, a 47-lot residential subdivision, on January 19, 2010 (Legistar File 09-1518). The tentative subdivision map had an original expiration date of January 19, 2013, which was automatically extended to January 19, 2017 due to state legislation (Assembly Bill AB 208 and 116). The Planning Commission subsequently approved six one-year time extensions on February 9, 2017 (Legistar File 09-1518) that resulted in a new expiration date. The map is due to expire on January 19, 2023. Based on substantial conformance review, the Development Services Director approved a revision to the map on March 7, 2017 to include an updated phasing plan and rearrangement of the lots (Exhibit C). No development has occurred and no final maps have been recorded.

 

In accordance with the Subdivision Map Act Section 66456, this Final Map would create a total of eight (8) large lots for phasing and financing purposes consistent with the approved tentative map (Exhibit D). No development is proposed at this time. No agreement to make subdivision improvements is necessary for approval of the Large Lot Final Map.

 

Given that no development is proposed with this request, none of the conditions are triggered and, therefore, not applicable to the approval of the Large Lot Final Map. Final map(s) for subsequent development phases based on the approved La Cañada Tentative Subdivision Map shall be further verified for conformance with all applicable conditions of approval under separate future small-lot final map applications.

 

Environmental Review:  The review of the Final Map is a ministerial process and is Statutorily Exempt from environmental review under Section 15268(b)(3) of the California Environmental Quality Act (CEQA) Guidelines. 

 

EXHIBITS (Attachment A)

 

Exhibit A - Location Map

Exhibit B - Assessor’s Parcel Map

Exhibit C - Approved Tentative Subdivision Map (TM08-1463-R)

Exhibit D - Large Lot Final Map for La Cañada Subdivision (TM08-1463)

 

ALTERNATIVES

N/A

 

PRIOR BOARD ACTION

See Discussion/Background Section above.

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

Surveyor and Department of Transportation

 

CAO RECOMMENDATION

It is recommended that the Board approve this item. 

 

FINANCIAL IMPACT

N/A

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

N/A

 

STRATEGIC PLAN COMPONENT​

Good Governance

 

CONTACT

Tiffany Schmid, Director

Planning and Building Department