File #: 19-0683    Version: 1
Type: Agenda Item Status: Approved
File created: 4/17/2019 In control: Board of Supervisors
On agenda: 5/14/2019 Final action: 5/14/2019
Title: Department of Transportation recommending the Board authorize the Chair to sign the Credit and Reimbursement Agreement for the Construction of Saratoga Way (Station 9+82 to Station 39+23) between the County and Elliott Homes, Inc. (AGMT 18-54896). FUNDING: Traffic Impact Mitigation Fees.
Attachments: 1. A - Approved CRS, 2. B - PE Reimbursement Agrmt, 3. C - Saratoga Estates COA, 4. D - Saratoga Estates DA, 5. Executed Agreement 18-54896
Related files: 16-0533, 18-0541, 20-0328
Title
Department of Transportation recommending the Board authorize the Chair to sign the Credit and Reimbursement Agreement for the Construction of Saratoga Way (Station 9+82 to Station 39+23) between the County and Elliott Homes, Inc. (AGMT 18-54896).

FUNDING: Traffic Impact Mitigation Fees.
Body
DISCUSSION / BACKGROUND
On September 13, 2016 (Item 36), the Board approved the Saratoga Estates Tentative Map, TM14-1520 and the Community Benefit and Development Agreement, DA15-0001 (Development Agreement), with Sunset Tartesso, LLC, a subsidiary of Elliott Homes, Inc. (Developer) allowing for the development of 317 residential units.

On November 18, 2016, the County executed the Development Agreement which established various responsibilities for the development including construction of the Saratoga Way off-site improvements (Project) from the intersection of the existing Saratoga Way to the point of connection with Iron Point Road in the City of Folsom. Specifically, Condition 49 of the Conditions of Approval for the Saratoga Estates Tentative Map and Section 3, Subsection 3.2.1 of the Development Agreement, require the Developer to construct the Project. The Project is a scheduled project within the County’s Capital Improvement (CIP) and Traffic Impact Mitigation (TIM) Fee programs.

As the previously approved Development Agreement and Road Improvement Agreements outline the County and Developers overall obligations related to the Saratoga Estates Development Project and design, construction and general funding of the Saratoga Way extension project respectively, this Reimbursement Agreement details more specifically the terms and conditions of reimbursements, time-lines, updated estimates and other funding specific provisions. A separate Reimbursement Agreement is required by the County's TIM Fee Program Guidelines and is a condition of the earlier approved Development Agreement. Approval of this agreement will aid the County and Developer in completin...

Click here for full text