Title
Department of Transportation recommending the Board:
1) Approve and authorize the Chair to sign the Notice of Acceptance with Doug Veerkamp General Engineering Inc., for the Pollock Pines - Pony Express Trail Bicycle, Pedestrian, and ADA Improvements Project, Contract 7451, CIP 97019/36109010; and
2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period.
(District 5)
FUNDING: Congestion Mitigation and Air Quality Program (29.9%), Active Transportation Program (28.2%), Regional Surface Transportation Program Federal Funds - Caltrans Local Assistance (17.3%), Tribe Funds (8.4%), Transportation Development Act (7.3%), and Road Fund (8.9%). (Federal Funds).
Body
DISCUSSION / BACKGROUND
The contract for the Pollock Pines - Pony Express Trail Bicycle, Pedestrian, and ADA Improvements Project (Project) was approved by the Board on October 10, 2023 (Legistar file 23-1256). Work was completed on January 27, 2025. Recordation of the Notice of Acceptance (NOA) will start legal time frames for guarantees, a lien period, and return of retention monies. Recordation of the NOA will also start the one-year time frame for releasing the Payment and Performance Bonds to the Surety.
Direct Construction Cost Summary:
Original Bid Price $2,945,688.00
Contract Item Cost $2,867,695.73
Contract Change Order Cost $ 115,626.42
Total Direct Construction Cost $2,983,322.15
Direct Construction Budget $3,000,112.00
Major Contract Change Orders on the Project dealt with the following:
• Additional grading to conform the existing dirt and paved trail segments with new trail segments
• Replacing planned recessed thermoplastic with painted markings
• Additional slurry seal between Sander Dr and Cox St to rehabilitate existing trail segments
• Fortify damaged or inadequate poles on flashing crosswalk beacons
The final costs listed are estimates. Transportation will be closing out the Project with the Contractor and finalizing costs over the coming weeks. Any significant deviations from the estimates above that exceed Transportation’s allocated authority will be brought back to the Board for review and approval in a subsequent agenda item.
ALTERNATIVES
The Board could choose not to approve the NOA. Transportation staff would make modifications as directed by the Board and return for Board approval of the NOA. This would delay the release of the Payment and Performance Bonds and extend the Contractor’s warranty period.
PRIOR BOARD ACTION
As outlined in Discussion/Background section above.
OTHER DEPARTMENT / AGENCY INVOLVEMENT
N/A
CAO RECOMMENDATION
Approve as recommended.
FINANCIAL IMPACT
There is no change to Net County Cost associated with this item. The Project is budgeted in Transportation’s 2024 CIP, which was approved by the Board on June 18, 2024 (Legistar file 24-0838).
CLERK OF THE BOARD FOLLOW UP ACTIONS
1) The Clerk of the Board will obtain the Chair’s signature on one (1) original of the NOA.
2) The Clerk of the Board will send the fully executed original of the NOA to the Recorder/Clerk’s Office for recordation within ten (10) days, and forward a copy of the recorded NOA to Transportation, Fairlane Engineering, Attention: Lindsay Tallman.
3) One (1) year after the recordation of the NOA, Transportation will verify that all warranty work, if any, has been satisfactorily completed and will notify the Clerk of the Board in writing to release the Payment and Performance Bonds.