Legislation Details

File #: 26-0236    Version: 1
Type: Agenda Item Status: Department Matters
File created: 1/21/2026 In control: Board of Supervisors
On agenda: 4/28/2026 Final action:
Title: Department of Transportation, Maintenance and Operations Division, recommending the Board: 1) Approve the transfer of the remaining fund balance in the Barnett Business Park Lighting Zone of Benefit 98534 into the general CSA 9 fund to reduce administrative costs; and 2) Direct staff to return to the Board with a Budget Transfer by June 30, 2026. FUNDING: Barnett Business Park Zone of Benefit Assessment. (100%)
Related files: 25-1200, 25-1199, 08-1093
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Department of Transportation, Maintenance and Operations Division, recommending the Board:

1) Approve the transfer of the remaining fund balance in the Barnett Business Park Lighting Zone of Benefit 98534 into the general CSA 9 fund to reduce administrative costs; and

2) Direct staff to return to the Board with a Budget Transfer by June 30, 2026.

 

FUNDING:  Barnett Business Park Zone of Benefit Assessment. (100%)

Body

DISCUSSION / BACKGROUND

The Board formed the Barnett Business Park Zone of Benefit 98534 (Zone) on October 7, 1986, by Resolution 316-86, in response to a petition submitted by the property owners to form the Zone to fund street lighting services.

 

On November 18, 2025, following a public hearing with no protests from affected parcel owners, the Board dissolved the zone by Resolution 169-2025 and directed staff to evaluate alternative methods for distributing the remaining fund balance and to return with a recommendation.

 

It is projected that the zone's account balance will be approximately $32,500 on June 1, 2026. Ideally, the funds could be transferred to a single business-owner entity (e.g., a Business Owners Association) for the express purpose of funding street lighting operations within the territory. However, no such entity exists in the Barnett Business Park.

                     

Staff recommends transferring the remaining funds to the General CSA 9 fund to support similar services and reduce administrative costs in the CSA. This approach is consistent with CSA law. A budget transfer will be brought back to the Board by June 30, 2026.

                     

ALTERNATIVES

The Board could choose an alternative action below or give staff further direction.

1. Refund the current parcel owners

                     May require funding agreements to ensure funds are used for their original purpose under CSA law;

                     A formal claim process with a sunset date may be necessary to ensure all checks will be cashed;

                     Estimated County costs: $5,900 (outreach, agreements, additional Board items, monitoring account balances, payment processing, check printing costs, postage, etc.); and

                     Net refund per parcel: approximately $400.

 

2. Request the Auditor-Controller establish a reimbursement account

                     Business owners could be reimbursed for the costs paid toward street lighting services on their parcel(s);

                     Would require ongoing payment processing until funds are depleted, potentially over several years; and

                     Higher administrative burden than Option 1 due to the length of time required to draw down the funds.

 

PRIOR BOARD ACTION

July 29, 2008, Legistar file 08-1093, Majority protest received during assessment ballot proceeding. Staff were directed to turn off the lights due to insufficient funding.

October 21, 2025, Legistar file 25-1199, Board approval of Resolution of Intent to Dissolve the Barnett Business Park Lighting Zone of Benefit

November 18, 2025, Legistar file 25-1200, Public hearing and dissolution of the Barnett Business Park Lighting Zone of Benefit

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

County Counsel

 

CAO RECOMMENDATION / COMMENTS

Approve as recommended.

 

FINANCIAL IMPACT

There is no impact to Net County Costs or other County resources. The costs associated with any of the provided options will be paid by the funds remaining in the zone's account which is estimated to be $32,500 on June 1, 2026.

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

N/A

 

STRATEGIC PLAN COMPONENT

N/A

 

CONTACT

Rafael Martinez, Director

Department of Transportation