File #: 26-0243    Version: 1
Type: Agenda Item Status: Consent Calendar
File created: 1/22/2026 In control: Board of Supervisors
On agenda: 2/10/2026 Final action:
Title: Department of Transportation recommending the Board approve and authorize the Board to execute Contract Change Order 3, Supplement 1, with A. Teichert & Son, Inc., dba Teichert Construction in the amount of $500,000 for the Diamond Springs Parkway - Phase 1B Project, Capital Improvement Program number 72334/36105011, Contract number 6558. (4/5 vote required) (District 3) FUNDING: Master Circulation and Funding Plan (58%), Traffic Impact Fees - Zone 1-7 (21%), State Local Partnership Program (14%), Regional Surface Transportation Program (3%), State Highway Operation and Protection Program (3%), Tribe Funds (historical <1%), and Road Fund (<1%). (Local and State Funds)
Attachments: 1. A - Contract Change Order 3-1
Related files: 24-1806, 24-0854, 23-2048, 25-2069, 25-0053, 25-0460
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Department of Transportation recommending the Board approve and authorize the Board to execute Contract Change Order 3, Supplement 1, with A. Teichert & Son, Inc., dba Teichert Construction in the amount of $500,000 for the Diamond Springs Parkway - Phase 1B Project, Capital Improvement Program number 72334/36105011, Contract number 6558. (4/5 vote required)

(District 3)

 

FUNDING:  Master Circulation and Funding Plan (58%), Traffic Impact Fees - Zone 1-7 (21%), State Local Partnership Program (14%), Regional Surface Transportation Program (3%), State Highway Operation and Protection Program (3%), Tribe Funds (historical <1%), and Road Fund (<1%).  (Local and State Funds)

Body

DISCUSSION / BACKGROUND

The Diamond Springs Parkway - Phase 1B Project (Project) will provide a new four-lane arterial roadway from Missouri Flat Road to State Route 49. On April 1, 2025 (Legistar 25-0460), the Board awarded construction contract 6558 to A. Teichert & Son, Inc., dba Teichert Construction (Teichert) in the amount of $15,853,114. The Board also awarded budgets of $1,585,311.40 for supplemental contract change orders (CCO) and $1,585,311.40 for contingency CCOs. The total amount to date of supplemental CCOs that have been issued is $886,009.00. No CCOs under the contingency budget have been issued. In accordance with Resolution 102-2012, the maximum authority delegated to the Director of Transportation for approval of a single CCO is $210,000.

 

On December 4, 2025, the Director of Transportation authorized Contract Change Order 3 (CCO 3) for temporary water pollution control measures in the amount of $200,000.  To date, a total of $191,533.68 has been paid under CCO 3 for site stabilization work as required by the contract documents. As additional temporary water pollution control work is anticipated through the remainder of the winter season, this CCO 3, Supplement 1 (CCO 3-1) is required in order to continue to compensate Teichert to implement the work. After issuance of CCO 3-1 for $500,000.00, the remaining supplemental CCO budget will be $199,302.40. Teichert shall furnish, install, maintain, and remove temporary water pollution control measures for temporary soil stabilization, temporary sediment control, and temporary linear sediment barriers in accordance with the approved Storm Water Pollution Prevention Plan, as specified in Section 13, Water Pollution Control, of the Special Provisions and Standard Specifications. Water pollution control measures associated with stockpile management are excluded from payment under this change order.

 

ALTERNATIVES

N/A

 

PRIOR BOARD ACTION

1) April 23, 2024 (Legistar file 23-2048) - Approved PG&E Utility Agreement No. 2934.1L.

2) May 14, 2024 (Legistar file 24-0854) - Approved PG&E Utility Agreement No. 2934.1L with revisions.

3) November 12, 2024 (Legistar file 24-1806) - Approved First Amendment to PG&E Utility Agreement No. 2934.1L.

4) January 28, 2025 (Legistar file 25-0053) - Approved advertisement for the Project.

5) April 1, 2025 (Legistar file 25-0460) - Awarded the construction contract for the Project.

6) January 6, 2026 (Legistar file 25-2069) - Approved CCO 2.

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

N/A

 

CAO RECOMMENDATION

Approve as recommended.

 

FINANCIAL IMPACT

There is no change to net County cost associated with this item. Funding for this CCO is incorporated into the Project’s construction phase budget as part of the 2025 CIP approved by the Board on July 15, 2025 (Legistar file 25-0504).

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

1) The Clerk of the Board will obtain the Board Chair's signature on CCO 3-1.

2) The Clerk of the Board will return a fully executed copy of CCO 3-1 to Transportation, Fairlane Engineering, attention Staci Goodwalt, for further processing.

 

STRATEGIC PLAN COMPONENT

Priority: N/A

Action Item: N/A

 

CONTACT

Rafael Martinez, Director

Department of Transportation