File #: 22-1985    Version: 1
Type: Agenda Item Status: Approved
File created: 10/20/2022 In control: Board of Supervisors
On agenda: 12/6/2022 Final action: 12/6/2022
Title: Department of Transportation recommending the Board approve and authorize the Chair to sign Road Improvement Agreement 22-55030 for the Offsite Road Improvements on the Green Valley Road Frontage Project, CG330261, between the County and the Developer, EDH Green Valley Holdings LLC. FUNDING: Developer Funded.
Attachments: 1. A - Counsel Approval, 2. B - Agmt 22-55030, 3. C - Performance and L&M Bonds, 4. D - Project Improvement Plans, 5. Executed Agreement 22-55030

Title

Department of Transportation recommending the Board approve and authorize the Chair to sign Road Improvement Agreement 22-55030 for the Offsite Road Improvements on the Green Valley Road Frontage Project, CG330261, between the County and the Developer, EDH Green Valley Holdings LLC.

 

FUNDING:  Developer Funded.

Body

DISCUSSION / BACKGROUND

The EDH-Folsom Self Storage Project, S18-0012 / PD18-0002, also known as the Green Valley Road Frontage Project, CG330261 (Project) was approved by the Planning Commission on October 24, 2019. The Department of Transportation (Transportation) is recommending the Board approve and authorize the Chair to sign the Offsite Road Improvement Agreement for Green Valley Road Frontage Project, CG330261, Agmt #22-55030 (Agreement), between the County and EDH Green Valley Holdings LLC (Developer).

 

In accordance with the Conditions of Approval approved by the Planning Commission on October 24, 2019, the Developer shall construct a dedicated right turn lane, a bike lane and bike buffer zone, curb and gutter, and concrete sidewalk along Green Valley Road from Shadowfax Lane to Sophia Parkway. The Developer shall also construct driveway access to Green Valley Road and emergency-only driveway access onto Shadowfax Lane.

 

The work described in the Agreement is anticipated to start in Spring 2023, and onsite improvements will begin in Winter 2022.

 

Section 12.08.155(A)(3) of the El Dorado County Ordinance Code requires that any party constructing an improvement in the County right-of-way with an estimated cost exceeding $100,000 enters into a road improvement agreement with the County.  Approval of this Agreement will allow the Developer to make improvements as necessary to complete the project.

 

ALTERNATIVES

This Agreement is necessary for the Developer to construct the offsite road improvements along Green Valley Road. If the Agreement is not approved, the Developer would not be able to construct the necessary improvements.

 

PRIOR BOARD ACTION

N/A

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

County Counsel

 

CAO RECOMMENDATION / COMMENTS

Approve as recommended.

 

FINANCIAL IMPACT

The requested Board action has no associated fiscal impact or change to Net County Cost. The Developer will bear the cost of constructing the improvements in the proposed Agreement, and there shall be no reimbursement for the required improvements. The Developer has provided County satisfactory security in the form of Performance and Laborers and Materialmens Bonds.

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

1) The Clerk of the Board will obtain the Chair’s signature on two (2) originals of the Agreement.

2) The Clerk of the Board will return one (1) fully executed original Agreement to Department of Transportation, attn: Lindsay Tallman, for final processing.

 

STRATEGIC PLAN COMPONENT

Infrastructure

 

CONTACT

Rafael Martinez, Director

Department of Transportation