Title
Department of Transportation recommending the Board:
1) Accept the constructed improvements for the Shingle Springs Village Project as complete;
2) Reduce the total cash deposits (in lieu of Performance and Laborer and Materialmens Bonds) from $2,984,473.12 to $298,447.31, which is ten percent of the total cost of the improvements. This amount guarantees against any defective work, labor done, or defective materials furnished, which is to be released after one year if no claims are made;
3) Authorize the Community Development Services, Administration and Finance Division to release $2,686,025.81 in cash security at this time; and
4) Authorize the Community Development Services, Administration and Finance Division to release the remaining cash deposit after the required time period upon written request from the Department of Transportation.
FUNDING: Developer Funded.
Body
DISCUSSION / BACKGROUND
On June 28, 2016 (Item 51), the Board approved Site Plan Review (SPR) 15-0003/Shingle Springs Drive Improvements-Encroachment Permit submitted by the Shingle Springs Band of Miwok Indians Development Corporation (Tribe).
On June 27, 2017 (Item 59), the Board approved Road Improvement Agreement for Shingle Springs Village, SPR 15-0003, Offsite Improvements Agreement 17-54634 (RIA) with the Tribe to construct the necessary water, sewer, road and driveway access improvements. The improvements for the project have been inspected by the Department of Transportation (Transportation) and were found to be complete in accordance with the approved plans, specifications and requirements of the RIA.
In lieu of Performance and Laborer and Materialmens Bonds, the Tribe provided cash deposits in the amount of $2,984,473.12, half of which was specifically provided in lieu of Laborer and Materialmens Bonds. Transportation has received a lien release from the contractor verifying all payments have been made to persons furnishing labor, materials, or equipment. Therefore, Transportation is requesting the Board reduce the total cash security to $298,447.31 to guarantee against any defective work, labor done, or defective materials furnished, which is to be released after one year if no claims are made and authorize the release of $2,686,025.81 in cash security at this time.
ALTERNATIVES
None; when the Owner/Developer completes all improvements and the County inspects and approves those improvements, the County is then obligated to approve reduction of the cash security deposits (in lieu of Performance and Laborer and Materialmens Bonds), if necessary, and initiate the warranty period.
PRIOR BOARD ACTION
See Discussion / Background section above.
OTHER DEPARTMENT / AGENCY INVOLVEMENT
N/A
CAO RECOMMENDATION / COMMENTS
It is recommended that the Board approve this item.
FINANCIAL IMPACT
The requested Board action has no associated fiscal impact or change to Net County Cost.
CLERK OF THE BOARD FOLLOW UP ACTIONS
N/A
STRATEGIC PLAN COMPONENT
Infrastructure