Title: Department of Transportation recommending the Board approve and authorize the Clerk of the Board to reduce Performance Bond 800169856 pertaining to Silver Springs Unit 3, TM97-1330, from $5,972,747.00 to $1,081,215.55, representing 100% of the total remaining improvements. This amount guarantees against any defective work, labor done, or defective materials furnished. (District 1) FUNDING: Developer Funded.
Attachments: 1. A - Certificate of Partial Completion, 2. B - Agmt #24-55066 and Amd I
Related files: 25-0594, 24-0368
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Department of Transportation recommending the Board approve and authorize the Clerk of the Board to reduce Performance Bond 800169856 pertaining to Silver Springs Unit 3, TM97-1330, from $5,972,747.00 to $1,081,215.55, representing 100% of the total remaining improvements. This amount guarantees against any defective work, labor done, or defective materials furnished.

(District 1)

 

FUNDING: Developer Funded.

Body

DISCUSSION / BACKGROUND

On February 27, 2024 (Legistar file 24-0368), the Board approved the Agreement to Make Subdivision Improvements for Class 1 Subdivision Silver Springs Unit 3, TM97-1330 (SIA) between the County, Silver Springs, LLC, and TTLC El Dorado - Silver Springs, LLC. On June 17, 2025 (Legistar file 25-0594), the Board approved the First Amendment to the SIA, updating both the project owner and developer to Silver Springs 181 Venture, LLC (Owner). The Second Amendment to the SIA was executed on February 26, 2026, under the authority of Resolution 006-2026, extending the performance period from February 27, 2026, to February 27, 2027.

 

Department of Transportation's (Transportation) construction inspection staff has inspected the work and confirms the subdivision improvements are partially complete according to the plans and specifications for this development and per the conditions of the SIA. The Owner has requested the Performance Bond for the project be reduced commensurate with the work completed, and Transportation agrees the reduction is appropriate.

 

ALTERNATIVES

None; pursuant to the terms of the SIA between the County and Owner, upon receipt of a Certificate stating a portion of the public improvements agreed to be performed has been partially completed, and County inspection and approval of those improvements, the County is obligated to approve reduction of the bonds. 

 

PRIOR BOARD ACTION

See Discussion / Background section above.

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

N/A

 

CAO RECOMMENDATION / COMMENTS

approve as recommended.

 

FINANCIAL IMPACT

There is no fiscal impact or change to Net County Cost associated with the requested Board action.

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

The Clerk of the Board will reduce Performance Bond 800169856 to $1,081,215.55 and advise Transportation, attn.: Lindsay Tallman, and the Owner, Silver Springs 181 Venture, LLC, 110 Blue Ravine Road, Suite 150, Folsom, CA 95630, that it has been reduced.

 

STRATEGIC PLAN COMPONENT

Priority: N/A

Action Item: N/A

 

CONTACT

Rafael Martinez, Director

Department of Transportation