File #: 25-0563    Version: 1
Type: Agenda Item Status: Approved
File created: 3/14/2025 In control: Board of Supervisors
On agenda: 4/8/2025 Final action: 4/8/2025
Title: Department of Transportation recommending the Board take the following actions pertaining to the Oflyng Water Quality Project (located in Oflyng Drive) - Phase 2, Capital Improvement Program project number 36107016: 1) Award the Construction Contract to Parsons Walls, who was the lowest responsive, responsible bidder; 2) Approve and authorize the Chair to sign the Construction Contract in the amount of $203,723.40, subject to review and approval by County Counsel and Risk Management; and 3) Authorize the Director of Transportation to sign an Escrow Agreement, if requested by the Contractor and in accordance with Public Contract Code Section 22300, for the purpose of holding Contract retention funds. (District 5) FUNDING: United States Forest Service (82%), Conservancy Funds (1%), State Water Resource Control Board (4%), and Tahoe Regional Planning Agency/Water Quality (13%).
Attachments: 1. A - 9322 Addendum No 1 - FE, 2. B - 9322-BidSummary

Title

Department of Transportation recommending the Board take the following actions pertaining to the Oflyng Water Quality Project (located in Oflyng Drive)  - Phase 2, Capital Improvement Program project number 36107016:

1) Award the Construction Contract to Parsons Walls, who was the lowest responsive, responsible bidder;

2) Approve and authorize the Chair to sign the Construction Contract in the amount of $203,723.40, subject to review and approval by County Counsel and Risk Management; and

3) Authorize the Director of Transportation to sign an Escrow Agreement, if requested by the Contractor and in accordance with Public Contract Code Section 22300, for the purpose of holding Contract retention funds.

(District 5)

 

FUNDING:  United States Forest Service (82%), Conservancy Funds (1%), State Water Resource Control Board (4%), and Tahoe Regional Planning Agency/Water Quality (13%).

Body

DISCUSSION / BACKGROUND

The Oflyng Water Quality Project - Phase 2 (Project) site is within an existing residential development located in the unincorporated area of South Lake Tahoe, east of U.S. Highway 50/State Route 89, north of Pioneer Trail, west of Elks Club Drive, and south of Skyline Drive. The Project is part of an ongoing effort to retrofit County rights-of-way within the Lake Tahoe Basin with improvements that will reduce the amount of sediment that reaches Lake Tahoe. The Project will help to meet goals identified in the El Dorado County Stormwater Resource Plan and the Lake Tahoe Environmental Improvement Program.

 

A Mitigated Negative Declaration for the Project was adopted by the Board on February 26, 2019 (Legistar file 18-1761), in accordance with the California Environmental Quality Act.

 

All necessary environmental permits have been obtained for this Project.

 

Additional right of way did not need to be secured for the Project.

 

The Contract Documents include all required federal provisions.

 

Award and Sign Construction Contract with Lowest Responsive, Responsible Bidder:

On Tuesday, March 25, 2025 at 2:00 p.m., Department of Transportation (Transportation) opened bids for the Project.  Six (6) bids were received ranging from $203,723.40 to $425,777.00.

 

Transportation issued the all bidders letter on March 26, 2025, notifying the bidders of the recommendation to the board for award of the Contract to Parsons Walls (Contractor) and initiating the bid protest period.  The bid protest period ended with no protests filed.

 

Authorize the Director of Transportation (Director) to Sign Escrow Agreement:

Pursuant to Section 9-1.16F(1), "Retentions" of the Contract Documents, Transportation will retain five percent (5%) of the value of work done from each contractor payment (excluding mobilization payments) as security for the fulfillment of the Contract. Alternatively, Public Contract Code (PCC) Section 22300 provides that the Contractor may request that payment of retentions held be made directly to an escrow agent. The Contractor will receive the interest earned on the investment.

 

In accordance with these provisions, the Contractor may request in writing that the County make payment of retention funds directly into an escrow account, which would necessitate an escrow agreement. To help expedite this process, if requested by the Contractor, Transportation requests that the Board authorize the Director to execute the Escrow Agreement. Upon satisfactory completion of portions of the Contract and upon written notification from the Director, the Contractor will receive incremental releases from the Escrow Agent paid into the account and any interest earned thereon. A portion of the retention and interest will be retained in the escrow account until thirty-five (35) days after the recordation of the Notice of Acceptance of the Contract at which time, upon written notification, these funds will be released to the Contractor.

 

Contract Change Orders (CCOs):

In any contract there is a need to be able to make changes and the CCO process facilitates the ability to make necessary changes when needed within a contract.

 

Contingency CCOs:

With construction contracts, there is an expectation that unanticipated changes will be encountered once construction begins. To prepare for this, a 10% contingency budget is set aside. PCC Section 20142 and Resolution 102-2012 authorize the Director to execute individual CCOs, the maximum value of which is based on the original contract amount. This authority is also for a cumulative total of contingency CCOs not to exceed 10% of the original Contract value.

 

ALTERNATIVES

1) The Board could choose not to award the Contract and direct Transportation to re-advertise for construction bids.

2) The Board could choose to cancel the Project.

 

PRIOR BOARD ACTION

February 26, 2019 (Legistar file 18-1761), the Board adopted a Mitigated Negative Declaration for the Project.

 

March 4, 2025 (Legistar file 25-0138) the Board approved advertisement for the Project.

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

County Counsel and Risk Management

 

CAO RECOMMENDATION / COMMENTS

Approve as recommended.

 

FINANCIAL IMPACT

The total estimated combined cost for Project construction is $268,914.89 which includes construction items of work, supplemental items of work, construction management, inspection, materials testing, and contingencies.

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

1) Upon approval by County Counsel and Risk Management, Department of Transportation will forward two (2) originals of the Construction Contract #9322, together with the required bonds and insurance, and the approved Contract Routing Sheet to the Clerk for the Chair's signature.

2) The Clerk will forward one (1) fully executed Construction Contract to the Department of Transportation, attention of Jen Rimoldi, Office Engineer Group, for further processing.

 

STRATEGIC PLAN COMPONENT

N/A

 