Title: Department of Transportation recommending the Board approve and authorize the Chair to sign the Agreement between the El Dorado County Transportation Commission and the County of El Dorado for Fiscal Year 2023-24 Surface Transportation Block Grant Program Exchange Funds (X24-6157(086)) in the amount of $560,513 for the following projects: Diamond Springs Parkway - Phase 1B (District 3), Green Valley Road at Indian Creek - Bridge Replacement (District 4), Green Valley Road at Mound Springs Creek - Bridge Replacement (District 4), and Latrobe West Connector (District 2). FUNDING: Surface Transportation Block Grant Program Exchange Funds (X24-6157(086)).
Attachments: 1. A - Blue Routing Sheet 24-0963.pdf, 2. B - X24-6157(086) Agreement.pdf

Title

Department of Transportation recommending the Board approve and authorize the Chair to sign the Agreement between the El Dorado County Transportation Commission and the County of El Dorado for Fiscal Year 2023-24 Surface Transportation Block Grant Program Exchange Funds (X24-6157(086)) in the amount of $560,513 for the following projects: Diamond Springs Parkway  - Phase 1B (District 3), Green Valley Road at Indian Creek - Bridge Replacement (District 4), Green Valley Road at Mound Springs Creek - Bridge Replacement (District 4), and Latrobe West Connector (District 2).

 

FUNDING:  Surface Transportation Block Grant Program Exchange Funds (X24-6157(086)).

Body

DISCUSSION / BACKGROUND

As authorized by Section 182.6(g) of the Streets and Highway Code, the El Dorado County Transportation Commission (EDCTC) has entered into Agreement X24-6157(086) with the State of California through the Department of Transportation (Caltrans) to assign a defined portion of its annual Surface Transportation Block Grant Program (STBGP) apportionment to Caltrans in exchange for FY 2023-24 nonfederal State Highway Account funds. EDCTC is authorized to use these exchange funds to assist local agencies in promoting projects that otherwise qualify for STBGP funds.

 

These are projects that are scheduled to be in process in time to make use of the Regional Surface Transportation Program (RSTP) funds, which must be expended within a certain time frame from when the funding cycle was released. The projects listed to receive these STBGP exchange funds are as follows:

 

- Diamond Springs Parkway - Phase 1B (Fenix Number 36105011): $13,000

 

- Green Valley Road at Indian Creek - Bridge Replacement (Fenix Number 36105014): $200,000

 

- Green Valley Road at Mound Springs Creek - Bridge Replacement (Fenix Number 36105015): $222,513

 

- Latrobe West Connector (Fenix Number 36105084): $125,000

 

EDCTC is required to execute formal written agreements between EDCTC and STBGP Exchange Recipients and provide oversight of the program funds. The EDCTC received the FY 2023-24 STBGP Exchange Funds, which will be paid to the County per the formula-based distribution policy adopted by EDCTC on February 3, 2011, after approval by EDCTC and the execution of this Agreement. The expiration date of the funds is five (5) years from the date funds are allocated by EDCTC.

 

ALTERNATIVES

Until an item such as this is approved by the Board, the funding will remain unclaimed.

 

PRIOR BOARD ACTION

N/A

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

EDCTC

County Counsel

CAO - Community Development Finance and Administration

 

CAO RECOMMENDATION

Approve as recommended.

 

FINANCIAL IMPACT

Approval of this Agreement will allow the County to receive a total of $560,513 in STBGP funding to be used on the following Capital Improvement Program projects: Diamond Springs Parkway - Phase 1B, Fenix Number 36105011, $13,000; Green Valley Road at Indian Creek - Bridge Replacement, Fenix Number 36105014, $200,000; Green Valley Road at Mound Springs Creek - Bridge Replacement, Fenix Number 36105015, $222,513; Latrobe West Connector, Fenix Number 36105084, $125,000. Project financing plans in the CIP will be updated to reflect this revenue.

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

1) The Clerk of the Board will obtain the Chair’s signature on two (2) originals of the STBGP Agreement.

2) The Clerk of the Board will forward the two (2) partially-executed original Agreements to the CAO - Community Development Finance and Administration, for further processing.

 

STRATEGIC PLAN COMPONENT

Infrastructure, Good Governance

 

CONTACT

Rafael Martinez, Director