Title: Transportation Department recommending Chairman be authorized to sign Easement Acquisition Agreement For Public Purposes and Certificate of Acceptance for the related Deed from Randy Peace and Norma Peace, Husband and Wife, as Joint Tenants for APN 069-101-60; and authorize the Director of Transportation or his designee to execute the escrow instructions and any other related escrow documents pertaining to the transaction, including the payment of title and escrow fees for the Tennessee Creek Bridge Replacement Project No. 77109. FUNDING: Highway Bridge Program, Highway Safety Improvement Program Grants and the 2004 GP Traffic Impact Mitigation Fee program
Attachments: 1. A-VicinityMap, 2. B-BlueRoute, 3. C-EasementAcquisitionAgreement, 4. D-DeedandCertificateofAcceptance
Title
Transportation Department recommending Chairman be authorized to sign Easement Acquisition Agreement For Public Purposes and Certificate of Acceptance for the related Deed from Randy Peace and Norma Peace, Husband and Wife, as Joint Tenants for APN 069-101-60; and authorize the Director of Transportation or his designee to execute the escrow instructions and any other related escrow documents pertaining to the transaction, including the payment of title and escrow fees for the Tennessee Creek Bridge Replacement Project No. 77109.
 
FUNDING: Highway Bridge Program, Highway Safety Improvement Program Grants and the 2004 GP Traffic Impact Mitigation Fee program
Body
BUDGET SUMMARY:
 
 
Total Estimated Cost
 
$1,200.00
 
 
 
     Funding
 
 
          Budgeted
$1,200.00
 
          New Funding
$
 
          Savings
$
 
          Other
$
 
     Total Funding Available
$1,200.00
 
Change To Net County Cost
 
$0
      
Fiscal Impact/Change to Net County Cost:
Acquisition costs are $500, with title and escrow fees of $700, for a total estimated cost of $1,200. The Tennessee Creek Bridge Replacement Project #77109 is funded with Highway Bridge Program (HBP), Highway Safety Improvement Program (HSIP) Grants and the 2004 GP Traffic Impact Mitigation Fee program (TIM) and sufficient funds are in the project budget for the subject acquisitions.  There is no net cost to the County General Fund associated with this agenda item.
 
Background:
The Department of Transportation (DOT) has been working to advance this grant funded project for the improvement, signalization, and channelization of the 3-way intersection of Green Valley Road and North Shingle Road and replacing the two-lane, reinforced concrete girder bridge with a three-lane, pre-stressed slab bridge.  Green Valley Road will be realigned to improve site distance and a continuous left turn median will extend from the North Shingle Road Intersection past Peaceful Garden Way and transition into the northbound lane prior to Oakvale Drive.
 
The project is subject to the California Environmental Quality Act (CEQA) and the National Environmental Policy Act (NEPA).  The preparation of a CEQA mitigated Negative Declaration and NEPA Categorical Exemption has been completed and on December 9, 2008, your Board adopted and approved the project as described in the CEQA and NEPA documents.
 
Reason for Recommendation:
On January 27, 2009, your Board authorized DOT's Right of Way unit staff to proceed with final negotiations to acquire the land rights from the subject property owners.  Negotiations with Randy Peace and Norma Peace have concluded and a settlement has been reached that is representative of the appraised value of the necessary land rights.
 
Action to be taken following Board approval:
1. Chairman to execute the Easement Acquisition Agreement for Public Purposes and the Certificate of Acceptance for the Temporary Construction Easement.
2. Board Clerk to return all executed documents to the DOT R/W unit for final processing.
3. Director of Transportation or designee to sign the Escrow Instructions and any related escrow documents pertaining to this transaction.  All executed documents and all funds necessary to the close of escrow, to be provided to the title company for final audit and recording.
 
Contact: James W. Ware, P.E.
               Director of Transportation
 