File #: 21-0550    Version: 1
Type: Agenda Item Status: Approved
File created: 3/29/2021 In control: Board of Supervisors
On agenda: 5/4/2021 Final action: 5/4/2021
Title: Department of Transportation recommending the Board consider the following pertaining to the 2021 Various West Slope Pavement Rehabilitation Projects, Contract 5513: 1) Approve and adopt the Contract Documents; and 2) Authorize advertisement for bids. FUNDING: Road Repair and Rehabilitation Act 2017 (SB1-RMRA) (100%) (No Federal Funds).
Attachments: 1. A - Approved Blue Route, 2. B - Grind and Pave Contract Docs, 3. C - Location Maps
Related files: 21-1644, 21-1749, 21-0860
Title
Department of Transportation recommending the Board consider the following pertaining to the 2021 Various West Slope Pavement Rehabilitation Projects, Contract 5513:
1) Approve and adopt the Contract Documents; and
2) Authorize advertisement for bids.

FUNDING: Road Repair and Rehabilitation Act 2017 (SB1-RMRA) (100%) (No Federal Funds).
Body
DISCUSSION / BACKGROUND
The purpose of the 2021 Various West Slope Pavement Rehabilitation Projects (Project) is to repair roadway sections in the South Lake Tahoe, Camino, Placerville, and Cameron Park areas of El Dorado County. The project includes approximately 90,000 square feet of sections on Mosquito Road, 130,000 on Sawmill Road, 100,000 on Carson Road, and 65,000 on Greenstone road and Greenstone Cutoff Road (see Attachment A, Exhibit C). The rehabilitation work will remove failing asphalt sections and replace with hot mix asphalt. Due to current Americans with Disability Act (ADA) requirements and regulations, all existing non-standard curb ramps within the Project area are required to be brought up to current standards as part of the Project.

This Project does not have federal funding, thus only California Environmental Quality Act (CEQA) compliance is required. A CEQA Notice of Exemption was filed on March 15, 2021. This Project does not require any environmental permits or additional right of way to be acquired.

ALTERNATIVES
1) The Board could choose to not approve the Contract Documents. Transportation will make any changes requested by the Board and return at a later date.
2) The Board could choose to not authorize advertisement for construction bids. Transportation will make any changes requested by the Board and return at a later date.
3) The Board could choose to cancel the Project. Canceling the Project would be contradictory to the Resolution the Board approved and authorized for Fiscal Year 2020-21 submittal to the State of California.

PRIOR BOARD ACTION
N/A

OTHER DEPARTMENT / AGENCY INVOLV...

Click here for full text