Title: Department of Transportation recommending the Board take the following actions pertaining to Contract 9966 for the 2026 DOT SLT Maintenance Pavement Rehabilitation Projects on Cedar Ridge Road, Pioneer Trail Frontage Road, Washoan Boulevard, Thunderbird Drive, Southern Pines Drive, Navahoe Drive, E San Bernardino Avenue, San Diego Street, Hopi Avenue, Bellevue Avenue, Scenic Drive, Tahoe Mountain, Mt Diablo Circle, Granite Mountain Circle and Mountain Meadows Drive: 1) Award the Construction Contract to Consolidated Engineering, Inc. the lowest responsive, responsible bidder; 2) Approve and authorize the Chair to sign the Construction Contract in the amount of $1,481,957.10, subject to review and approval by County Counsel and Risk Management; and 3) Authorize the Director of Transportation to sign an Escrow Agreement, if requested by the Contractor and in accordance with Public Contract Code Section 22300, for the purpose of holding Contract retention funds. (District 5) FUNDING: T...
Attachments: 1. A - BID SUMMARY #9966
Related files: 25-1920
Title
Department of Transportation recommending the Board take the following actions pertaining to Contract 9966 for the 2026 DOT SLT Maintenance Pavement Rehabilitation Projects on Cedar Ridge Road, Pioneer Trail Frontage Road, Washoan Boulevard, Thunderbird Drive, Southern Pines Drive, Navahoe Drive, E San Bernardino Avenue, San Diego Street, Hopi Avenue, Bellevue Avenue, Scenic Drive, Tahoe Mountain, Mt Diablo Circle, Granite Mountain Circle and Mountain Meadows Drive:
1) Award the Construction Contract to Consolidated Engineering, Inc. the lowest responsive, responsible bidder;
2) Approve and authorize the Chair to sign the Construction Contract in the amount of $1,481,957.10, subject to review and approval by County Counsel and Risk Management; and
3) Authorize the Director of Transportation to sign an Escrow Agreement, if requested by the Contractor and in accordance with Public Contract Code Section 22300, for the purpose of holding Contract retention funds.
(District 5)

FUNDING: Transient Occupancy Tax - Measure S (67%) and Road Fund (33%). (No Federal Funds)
Body
DISCUSSION / BACKGROUND
The purpose of the 2026 DOT SLT Maintenance Pavement Rehabilitation Projects (Project) is to repair various roadway sections on Cedar Ridge Road, Pioneer Trail Frontage Road, Washoan Boulevard, Thunderbird Drive, Southern Pines Drive, Navahoe Drive, E San Bernardino Avenue, San Diego Street, Hopi Avenue, Bellevue Avenue, Scenic Drive, Tahoe Mountain, Mt Diablo Circle, Granite Mountain Circle and Mountain Meadows Drive in South Lake Tahoe and Tahoma areas of El Dorado County by removing the failing asphalt section and replacing with hot mix asphalt.

Contract working hours will be between the hours of 7:00 am and 7:00 pm Monday through Friday, unless otherwise authorized. Reversing controls will be used during the Project.

All work will be performed within existing County right of way, and no additional right of way is needed. A California Environmental Quality Act ...