File #: 21-1763    Version: 1
Type: Agenda Item Status: Approved
File created: 10/29/2021 In control: Board of Supervisors
On agenda: 11/16/2021 Final action: 11/16/2021
Title: Department of Transportation recommending the Board approve the attached amendment to the Funding, Credit, and Reimbursement Agreement between West Valley, LLC and the County of El Dorado, amending payment terms to allow for quarterly rather than annual reimbursement payments. FUNDING: Traffic Impact Fee Program (Silva Valley Set Aside).
Attachments: 1. A - West Valley First Amendment, 2. B - Original Funding Agmt - WV, 3. C - West Valley Amendment I BR
Related files: 22-0423
Title
Department of Transportation recommending the Board approve the attached amendment to the Funding, Credit, and Reimbursement Agreement between West Valley, LLC and the County of El Dorado, amending payment terms to allow for quarterly rather than annual reimbursement payments.

FUNDING: Traffic Impact Fee Program (Silva Valley Set Aside).
Body
DISCUSSION / BACKGROUND
The Department of Transportation (Transportation) and West Valley LLC (Developer), entered into a Funding, Credit, and Reimbursement Agreement, as approved by the Board of Supervisors on November 8, 2005 (Item 21). Under this agreement, the Developer advanced funding to construct portions of the Silva Valley Interchange project as conditioned by the West Valley residential development project. Those funds were advanced by the Developer, and the County constructed the interchange improvements. The reimbursement agreement stipulated that the Developer would be reimbursed certain costs for the project on an annual basis as Traffic Impact Fees accumulate in the Silva Valley Set Aside account. These funds are to be distributed annually, no later than March 1st of each year, based on available funding as of December 31st of the previous year, until full reimbursement has been made, per section 6 of the agreement.

Transportation takes no exception to advanced reimbursement, provided sufficient funds are reserved to complete the remaining elements of the project. As of October 1, 2021, there is approximately $1,325,000 available for reimbursement to the Developer while retaining sufficient funds for remaining project requirements. The attached amendment will allow for quarterly reimbursement payments vs. annual payments.

For reference, the Developer is currently owed approximately $3.5 million in reimbursement. If approved, this payment of $1.325 million will reduce the remaining reimbursement to approximately $2.175 million. The Silva Valley Set Aside accrued approximately $1.8 milli...

Click here for full text