File #: 24-1436    Version: 1
Type: Agenda Item Status: Approved
File created: 8/1/2024 In control: Board of Supervisors
On agenda: 9/10/2024 Final action: 9/10/2024
Title: Department of Transportation recommending the Board consider the following: 1) Approve and authorize the Chair to sign the Notice of Acceptance with Hanford Applied Restoration & Conservation for the US 50 / Missouri Flat Road Interchange Improvements - Phase 1C- Riparian Restoration Project, Capital Improvement Program 36104014, Contract 73; and 2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period. (District 3) FUNDING: Master Circulation & Funding Plan Financing (100% - Local).
Attachments: 1. A - Notice of Acceptance.pdf, 2. Executed Notice of Acceptance
Related files: 16-0455
Title
Department of Transportation recommending the Board consider the following:
1) Approve and authorize the Chair to sign the Notice of Acceptance with Hanford Applied Restoration & Conservation for the US 50 / Missouri Flat Road Interchange Improvements - Phase 1C- Riparian Restoration Project, Capital Improvement Program 36104014, Contract 73; and
2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period.
(District 3)

FUNDING: Master Circulation & Funding Plan Financing (100% - Local).
Body
DISCUSSION / BACKGROUND
The contract for the US 50 / Missouri Flat Road Interchange Improvements - Phase 1C- Riparian Restoration Project (Project) was approved by the Board on August 2, 2016, Legistar File 16-0455. Construction started on October 10, 2016, and was completed in December 2018. The Plant Establishment period began January 15, 2018, and ended December 31, 2023. Due to extensive coordination with the California Department of Fish and Wildlife, revisions to the success criteria, and the overall difficulty in plant establishment in high scour areas, the plant establishment period was extended from its anticipated completion in January 2022 to December 2023. All field and reporting work is now complete. The recordation of the Notice of Acceptance (NOA) will start legal time frames for guarantees, a lien period, and return of retention monies. Recordation of the NOA will also start the one-year time frame for releasing the Payment and Performance Bonds to the Surety.

Direct Construction Cost Summary:

Original Bid Price $ 679,892
Contract Item Cost $ 577,498
Contract Change Order Cost $ 157,578
Total Direct Construction Cost $ 735,076
Direct Construction Budget $ 794,909

Major Contract Change Orders (CCO) on the Project dealt with the following:
· Locate Irrigation Crossovers;
· Temporary Su...