Department of Transportation recommending the Board authorize the Chair to sign the Reimbursement Agreement for the construction of the "Road Widening Improvement Plans for the Crossings at El Dorado Missouri Flat and Crossings Road" between the County and LLL & A, LLC (AGMT 22-55037), for improvements included in CIP Project 36105066 "Missouri Flat Widening from Plaza Drive to Headington Road." (District 3)
FUNDING: Missouri Flat Area Master Circulation & Funding Plan (MC&FP) Program.
Body
DISCUSSION / BACKGROUND
The Crossings at El Dorado, also known as the Crossings Planned Development, PD97-0011 (Project), is a commercial development project located on Missouri Flat Road in the unincorporated area of Placerville adjacent to the Target and Safeway shopping centers. The initial development was approved as the "Sundance Plaza" project on December 8, 1998. On May 8, 2014, the Planning Commission approved a Finding of Consistency on the Project, which updated the project phasing to its current structure and the project name to "The Crossings at El Dorado."
The Project requires access from Missouri Flat Road, which necessitates widening Missouri Flat Road, adding turn lanes, signalizing the existing Headington / Missouri Flat Road intersection, and adding an extension of Headington Road (referred to as Crossings Lane in Attachment E) as the fourth leg of the intersection and access to the development. These improvements are included in the Capital Improvement Program (CIP) as projects #36105066/71374, "Missouri Flat Widening from Plaza Drive to Headington Road," and #36105022/71375, "Headington Road Extension - Missouri Flat Road to El Dorado Road."
LLL& A, LLC (Developer) has prepared improvement plans for the intersection, which the Department of Transportation (Transportation) approved on May 9, 2022. On August 30, 2022 (Legistar# 22-1539, Item 17), the County and the Developer entered into Road Improvement Agreement (RIA) #21-54981 defining the ...