Title
Department of Transportation, Maintenance and Operations Division, recommending the Board:
1) Approve and authorize the Chair to sign the Notice of Acceptance with Kingsborough Atlas Tree Surgery for the 2022 Caldor Fire Hazardous Tree Removal within County Right of Way, Contract 7039; and
2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation after the one-year guarantee period.
FUNDING: General Fund Set Aside (100%). Potential reimbursement of Federal Emergency Management Agency funding (90%), California Governor's Office of Emergency Services funding (7.5%) and General Fund Set Aside (2.5%).
Body
DISCUSSION / BACKGROUND
The Board approved the contract for the Project on December 13, 2022 (Legistar #22-1922). All arborist-identified hazardous trees within the County's right of way were removed by May 1, 2023. Recordation of the Notice of Acceptance (NOA) will start legal time frames for guarantees, a lien period, and return of retention monies. Recordation of the NOA will also begin the one-year time frame for releasing the Payment and Performance Bonds to the Surety.
Direct Construction Cost Summary:
Original Bid Price $1,172,573.60
Contract Item Cost $1,076,366.50
Contract Change Order Cost $0.00
Total Direct Construction Cost $1,076,366.50
Direct Construction Budget $1,172,573.60
Major Contract Change Orders on the Project were not necessary.
ALTERNATIVES
The Board could choose not to approve the NOA. Transportation staff would make modifications as directed by the Board and return for Board approval of the NOA. This would delay the release of the Payment and Performance Bonds and extend the Contractor’s warranty period.
PRIOR BOARD ACTION
#22-1922 12/13/22 - Award Contract
OTHER DEPARTMENT / AGENCY INVOLVEMENT
N/A
CAO RECOMMENDATION / COMMENTS
Approve staff recommendation.
FINANCIAL IMPACT
There is no change to Net County ...
Click here for full text