File #: 09-1523    Version:
Type: Agenda Item Status: Department Matters
File created: 12/18/2009 In control: Board of Supervisors
On agenda: 1/25/2010 Final action:
Title: Transportation Department recommending the Board direct the Department to take the following actions regarding the U.S. Highway 50/Cameron Park Drive Interchange projects (CIP Project Nos. 72361 and 72367): 1) Explore additional alternatives that would: a) Reduce the impacts on surrounding businesses and residences; and b) Reduce the cost of these projects from the current estimate of $68 million; and 2) Return to the Board with more information at appropriate points to discuss findings and seek direction.
Attachments: 1. A - Cam Park Dr Interchange Pres 1-25-10 v22.pdf
Related files: 18-0992
Title
Transportation Department recommending the Board direct the Department to take the following actions regarding the U.S. Highway 50/Cameron Park Drive Interchange projects (CIP Project Nos. 72361 and 72367):
1) Explore additional alternatives that would:
a) Reduce the impacts on surrounding businesses and residences; and
b) Reduce the cost of these projects from the current estimate of $68 million; and
2) Return to the Board with more information at appropriate points to discuss findings and seek direction.
Body
Fiscal Impact/Change to Net County Cost:
There is no fiscal impact nor change to net County Cost associated with this item. The Department will use TIM Fee Program revenues to research and analyze alternatives.

Background:
When the 2009 Capital Improvement Program (CIP) and the Traffic Impact Mitigation (TIM) Fee Resolution were adopted by the Board, on May 5, 2009 and June 2, 2009 respectively, the Department of Transportation (Department) committed to return to the Board to discuss the costs, issues, and alternatives associated with the following projects: U.S. 50/High Occupancy Vehicle (HOV) Lanes, U.S. 50/Silva Valley Interchange, and U.S. 50/Cameron Park Drive Interchange.

Although the total cost of the TIM Fee Program increased by 4.2% (+39.2M) from $942.9 million to $982.1 million, on June 2, 2009, the Department recommended and the Board approved that there be no change in the TIM fees. The U.S. 50/Cameron Park Drive Interchange project is one possible area that could help close the $39.2M gap.

Reason for Recommendation:
In order to achieve a twenty year Level of Service (LOS) of E or better at the Cameron Park Drive Interchange, the cost estimate for CIP Projects #72361 U.S. 50/Cameron Park Drive Interchange Improvements Phase 1 and #72367 Cameron Park Widening - 3-Lane Divided to Modified 4-Lane from Durock Road to Coach, has risen from $24.8M in March, 2006 to $68M now, based upon information produced for the Project Study ...