File #: 13-0527    Version: 1
Type: Agenda Item Status: Approved
File created: 5/3/2013 In control: Board of Supervisors
On agenda: 5/21/2013 Final action: 5/21/2013
Title: Transportation recommending the Board consider the following: 1) Authorize the Chair to sign the Acquisition Agreement for Public Purposes and the Certificates of Acceptance for the related documents from Tower Energy Group, a California Corporation, for Assessor's Parcel Numbers 329-280-12 and 329-280-13, subject to County Counsel review and approval; and 2) Authorize the Director of Transportation or designee to execute the escrow instructions and any other related escrow documents pertaining to the transaction, including payment of title and escrow fees, for the Pleasant Valley Road (SR49)/Patterson Drive Intersection Signalization Project, CIP No. 73320. FUNDING: 2004 General Plan Traffic Impact Mitigation Fees.
Attachments: 1. A - Draft CRS 5-21-13, 2. B - Acquisition Agreement 5-21-13, 3. Fully executed Acquisition Agreement.pdf, 4. Fully executed Grant Deed 329-280-13.pdf, 5. Fully executed Highway and PUE Deed 329-280-13.pdf, 6. Fully executed PUE 329-280-13 and 13.pdf, 7. Fully executed TCE 329-280-12 and 329-280-13.pdf, 8. Fully executed TCE 329-280-13.pdf
Title
Transportation recommending the Board consider the following:
1) Authorize the Chair to sign the Acquisition Agreement for Public Purposes and the Certificates of Acceptance for the related documents from Tower Energy Group, a California Corporation, for Assessor's Parcel Numbers 329-280-12 and 329-280-13, subject to County Counsel review and approval; and
2) Authorize the Director of Transportation or designee to execute the escrow instructions and any other related escrow documents pertaining to the transaction, including payment of title and escrow fees, for the Pleasant Valley Road (SR49)/Patterson Drive Intersection Signalization Project, CIP No. 73320.

FUNDING: 2004 General Plan Traffic Impact Mitigation Fees.
Body
BUDGET SUMMARY:
Total Estimated Cost…………… $90,000

Budgeted………………………… $90,000
New Funding…………………….
Savings…………………………
Other……………………………
Total Funding Available………… $90,000

Change To Net County Cost…… $0

Fiscal Impact/Change to Net County Cost
Acquisition costs are $3,415 for fee title, $2,848 for a Highway Easement, $27,010 for a Public Utility Easement, $16,560 for two Temporary Construction Easements, and $23,416 for damages which include relocating a fuel sign, light pole and irrigation controller main, with title and escrow fees estimated at $16,751 for a total of $90,000. Funding for the acquisition process will be provided by 2004 General Plan Traffic Impact Mitigation fees.

Background
The intersection of Pleasant Valley Road (State Route 49)/Patterson Drive is located approximately one mile northeast of the community of El Dorado and two miles northwest of the community of Diamond Springs on State Route 49. Currently the intersection is a three-way stop.

The Pleasant Valley Road (SR49)/Patterson Drive Intersection Signalization Project (Project) area consists of approximately 1,800 feet of Pleasant Valley Road (State Route 49) and approximately 850 feet of Patterson Drive. Proposed improvements include the...