File #: 25-0145    Version: 1
Type: Agenda Item Status: Approved
File created: 1/8/2025 In control: Board of Supervisors
On agenda: 2/11/2025 Final action: 2/11/2025
Title: Department of Transportation recommending the Board consider the following pertaining to the Pleasant Valley Road Safety Improvements Project, Capital Improvement Program project number 36105072, Contract 8596: 1) Approve and adopt the Plans and Contract Documents and authorize the Chair to sign the Plans; and 2) Authorize advertisement for construction bids. (District 3) FUNDING: Highway Safety Improvement Program - State (89%), RSTP Advance - EDCTC (11%) (No Federal Funds).
Attachments: 1. A - Contract Routing Sheet.pdf, 2. B - Contract Documents.pdf, 3. C - Plans.pdf, 4. Executed Plans
Related files: 25-0641
Title
Department of Transportation recommending the Board consider the following pertaining to the Pleasant Valley Road Safety Improvements Project, Capital Improvement Program project number 36105072, Contract 8596:
1) Approve and adopt the Plans and Contract Documents and authorize the Chair to sign the Plans; and
2) Authorize advertisement for construction bids.
(District 3)

FUNDING: Highway Safety Improvement Program - State (89%), RSTP Advance - EDCTC (11%) (No Federal Funds).
Body
DISCUSSION / BACKGROUND
The Pleasant Valley Road Safety Improvements Project will improve motorist safety along Pleasant Valley Road. Project improvements include application of high friction surface treatment at pertinent roadway segments as well as night-visibility enhanced centerline and edgeline striping. Additionally, the Project involves installing a rapid flashing beacon at the existing crosswalk across from Pleasant Valley Middle School and a flashing beacon on an existing sign at Manor Drive and Pleasant Valley Road.

This project is state funded, therefore only California Environmental Quality Act (CEQA) compliance is required. A CEQA Notice of Exemption was recorded on December 14, 2021.

No environmental permits, right of way, or DBE is needed for this Project. Authorization for construction funding has been received for this Project.

ALTERNATIVES
1) The Board could choose not to approve the Contract Documents. Transportation will make any changes requested by the Board and return at a later date.
2) The Board could choose not to authorize advertisement for construction bids. Transportation will make any changes requested by the Board and return at a later date.
3) The Board could choose to cancel the Project.

PRIOR BOARD ACTION
N/A

OTHER DEPARTMENT / AGENCY INVOLVEMENT
County Counsel and Risk Management have reviewed and approved the Plans and Contract Documents.

CAO RECOMMENDATION / COMMENTS
Approve as recommended.

FINANCIAL IMPACT
The total estimate...

Click here for full text