Title
Community Development Agency, Transportation Division, recommending the Board take the following actions related to the Silver Springs Parkway to Bass Lake Road (South Segment) Project, CIP 76108:
1) Receive a presentation containing an overview of the Project and the Subsequent Environmental Impact Report;
2) Certify the Final Subsequent Environmental Impact Report pursuant to the California Environmental Quality Act;
3) Adopt the Mitigation Monitoring and Reporting Plan;
4) Adopt the Findings of Fact;
5) Approve the Project as described in the Final Subsequent Environmental Impact Report; and
6) Authorize Transportation Division staff to proceed with final design, rights-of-way acquisition, permitting, and other activities for Project construction. (Est. Time: 20 Min.)
FUNDING: Project is funded by Developer Advance Traffic Impact Mitigation Funds (45%), Developer Funds (39%), Traffic Impact Mitigation Fees (15%), and Road Fund (1%). (No Federal Funds)
Body
DEPARTMENT RECOMMENDATION
Community Development Agency (CDA), Transportation Division (Transportation), recommending the Board take the following actions related to the Silver Springs Parkway to Bass Lake Road (South Segment), Capital Improvement Program (CIP) Project 76108 (Project):
1) Receive a presentation containing an overview of the Project and the Subsequent Environmental Impact Report;
2) Certify the Final Subsequent Environmental Impact Report (FSEIR) pursuant to the California Environmental Quality Act (CEQA);
3) Adopt the Mitigation Monitoring and Reporting Plan (MMRP);
4) Adopt the Findings of Fact;
5) Approve the Project as described in the FSEIR; and
6) Authorize Transportation staff to proceed with final design, rights-of-way acquisition, permitting, and other activities for Project construction.
The recommended Board actions are based on the attached CEQA Findings of Fact (Attachment D) and findings by Transportation (acting on behalf of the County, the CEQA lead agency for ...
Click here for full text