File #: 21-1644    Version: 1
Type: Agenda Item Status: Approved
File created: 10/8/2021 In control: Board of Supervisors
On agenda: 11/16/2021 Final action: 11/16/2021
Title: Department of Transportation, Maintenance and Operations Division, recommending the Board: 1) Approve and authorize the Chair to sign the Notice of Acceptance with Doug Veerkamp General Engineering, Inc., for the 2021 Various West Slope Pavement Rehabilitation Projects, Contract 5513; and 2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period. FUNDING: Local Discretionary/Tribe (15%) and Road Maintenance and Rehabilitation Act of 2017 (RMRA - SB1) (State) (85%).
Attachments: 1. A - NOA, 2. Executed Recorded NOA
Related files: 21-0860, 21-0550, 21-1749
Title
Department of Transportation, Maintenance and Operations Division, recommending the Board:
1) Approve and authorize the Chair to sign the Notice of Acceptance with Doug Veerkamp General Engineering, Inc., for the 2021 Various West Slope Pavement Rehabilitation Projects, Contract 5513; and
2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period.

FUNDING: Local Discretionary/Tribe (15%) and Road Maintenance and Rehabilitation Act of 2017 (RMRA - SB1) (State) (85%).
Body
DISCUSSION / BACKGROUND
The 2021 West Slope Various Pavement Rehabilitation Projects (Project) provided roadway failure repair to designated pavement sections on Sawmill Road, Carson Road, Greenstone Road, Greenstone Cutoff and Mosquito Road in preparation for surface treatments in the 2021 construction season. Work included paving approximately 386,070 square feet of asphalt, and bringing all existing non-standard curb ramps, within the Project area, up to current standards due to current Americans with Disabilities Act (ADA) requirements and regulations. The contract for the Project was approved by the Board on June 8, 2021 (Legistar# 21-0860, Item 40). All roadway repairs were completed by August 20, 2021. Recordation of the Notice of Acceptance (NOA) will start legal time frames for guarantees, a lien period, and return of retention monies. Recordation of the NOA will also start the one-year time frame for releasing the Payment and Performance Bonds to the Surety.

Direct Construction Cost Summary:

Original Bid Price $1,169,690.72
Contract Item Cost $1,162,185.70
Contract Change Order Cost $8,967.52
Total Direct Construction Cost $1,171,153.22
Direct Construction Budget $1,462,103.40

Contract Change Orders on the Project dealt with the following:
ยท ADA Curb Ramps in the Bar J area of Cameron Park

ALTERNATIVES
The Board could choose no...

Click here for full text