Legislation Details

File #: 26-0960    Version: 1
Type: Agenda Item Status: Time Allocation
File created: 5/26/2026 In control: Board of Supervisors
On agenda: 6/16/2026 Final action:
Title: HEARING - To consider three separate appeals (TM-A26-0001, TM-A26-0002, TM-A26-0003) received from 1) Dean Getz, 2) Gary Kinghorn, and 3) Tara Mccann appealing the Planning Commission’s May 14, 2026 approval of Tentative Subdivision Map/Planned Development Permit TM25-0003/PD25-0005/Serrano Village M5 subdivision of an existing 8.42-acre lot into 10 residential lots in the El Dorado Hills area. (District 1) Staff recommending the Board take the following action: 1) Uphold the Planning Commission approval of Tentative Subdivision Map/Planned Development Permit TM25-0003/PD25-0005/Serrano Village M5 (deny appeals TM-A26-0001, TM-A26-0002, and TM-A26-0003), based on the Findings of Approval adopted by the Planning Commission, as may be modified by the Board; and 2) Uphold the Planning Commission finding that the project is Statutorily Exempt pursuant to Section 15182 of the CEQA Guidelines. FUNDING: Privately funded appeal for applicant-funded project
Attachments: 1. A - Appeal Packet - TM-A26-0001.pdf, 2. B - Appeal Packet - TM-A26-0002.pdf, 3. C - Appeal Packet - TM-A26-0003.pdf, 4. E - PC Staff Report.pdf, 5. D - Staff Memo.pdf, 6. F - PC Findings.pdf, 7. G - PC Conditions of Approval.pdf, 8. H1 - PC Staff Report Exhibits A-E.pdf, 9. H2 - PC Staff Report Exhibits F-L.pdf, 10. H3 - PC Staff Report Exhibits M-N.pdf, 11. H4 - PC Staff Report Exhibits O-S.pdf, 12. I - Serrano Village M5 Access and Local Circulation Analysis.pdf, 13. J - Staff Presentation, 14. Public Comment BOS RCVD 6-11-2026
Related files: 19-1085, 19-1171, 19-1714, 21-0695, 25-0387, 26-0785, 25-1214
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
HEARING - To consider three separate appeals (TM-A26-0001, TM-A26-0002, TM-A26-0003) received from 1) Dean Getz, 2) Gary Kinghorn, and 3) Tara Mccann appealing the Planning Commission’s May 14, 2026 approval of Tentative Subdivision Map/Planned Development Permit TM25-0003/PD25-0005/Serrano Village M5 subdivision of an existing 8.42-acre lot into 10 residential lots in the El Dorado Hills area.
(District 1)

Staff recommending the Board take the following action:
1) Uphold the Planning Commission approval of Tentative Subdivision Map/Planned Development Permit TM25-0003/PD25-0005/Serrano Village M5 (deny appeals TM-A26-0001, TM-A26-0002, and TM-A26-0003), based on the Findings of Approval adopted by the Planning Commission, as may be modified by the Board; and
2) Uphold the Planning Commission finding that the project is Statutorily Exempt pursuant to Section 15182 of the CEQA Guidelines.

FUNDING: Privately funded appeal for applicant-funded project
Body
DISCUSSION / BACKGROUND
On May 14, 2026 (Legistar file 26-0785), the Planning Commission held a public hearing to consider a request for Serrano Village M5 subdivision on property identified by Assessor’s Parcel Number 123-020-023 (8.42 acres), in the El Dorado Hills area.

The Planning Commission approved TM25-0003/PD25-0005 with a vote of three (4) ayes and one (1) no.

Staff’s response to the appeal and conclusion is detailed in a Staff Memo attached as Attachment D.

ALTERNATIVES
Reverse the Planning Commission’s approval of TM25-0003/PD25-0005/Serrano Village M5 (approve appeals TM-A26-0001, TM-A26-0002, and/or TM-A26-0003) with Findings of Denial based upon the Board of Supervisors direction.

OTHER DEPARTMENT / AGENCY INVOLVEMENT
N/A

FINANCIAL IMPACT
An appeal fee of $450 has been collected for each appeal, TM-A26-0001, TM-A26-0002, TM-A26-0003; however, staff costs associated with this appeal exceed the collected fees. Approval of the project would allow for construction of 10 single-...

Click here for full text