File #: 22-0694    Version: 1
Type: Agenda Item Status: Approved
File created: 4/8/2022 In control: Board of Supervisors
On agenda: 6/14/2022 Final action: 6/14/2022
Title: Department of Transportation recommending the Board consider the following: 1) Approve and authorize the Chair to sign Road Improvement Agreement 22-55016 for Beatty Drive on the Ridgeview Village Unit 9 project, TM 08-1477, between the County and the Developer, The New Home Company Northern California LLC; and 2) Adopt and authorize the Chair to sign Resolution 074-2022 authorizing the temporary closure of a portion of Beatty Drive in El Dorado Hills for a period of one hundred-twenty (120) days for the purpose of the construction of road improvements, beginning no earlier than June 21, 2022. FUNDING: Developer Funded.
Attachments: 1. A - Counsel Approval for Agreement, 2. B - Agmt 22-55016, 3. C - Performance and L&M Bonds, 4. D - Project Improvement Plans, 5. E - Counsel Approval for Resolution, 6. F - Resolution for Closure of Beatty Drive, 7. G - Closure and Detour Map, 8. Executed Agreement 22-55016, 9. Executed Resolution 074-2022
Related files: 22-1909, 24-0713
Title
Department of Transportation recommending the Board consider the following:
1) Approve and authorize the Chair to sign Road Improvement Agreement 22-55016 for Beatty Drive on the Ridgeview Village Unit 9 project, TM 08-1477, between the County and the Developer, The New Home Company Northern California LLC; and
2) Adopt and authorize the Chair to sign Resolution 074-2022 authorizing the temporary closure of a portion of Beatty Drive in El Dorado Hills for a period of one hundred-twenty (120) days for the purpose of the construction of road improvements, beginning no earlier than June 21, 2022.

FUNDING: Developer Funded.
Body
DISCUSSION / BACKGROUND
The Tentative Map (TM 08-1477) for the Ridgeview Village, Unit 9 project (Project) was approved by the Planning Commission on October 24, 2019. Department of Transportation (Transportation) is recommending the Board approve and authorize the Chair to sign the Beatty Drive, TM 08-1477 Road Improvement Agreement 22-55016 (Agreement), between the County and The New Home Company Northern California LLC (Developer).

Road Improvement Agreement
In accordance with the Conditions of Approval approved by the Planning Commission on October 24, 2019, the Developer shall widen and improve Beatty Drive including adding curb and gutter along the length, installing sidewalks on the downhill side, adding traffic signs, restriping the roadways, and installing water lines, sewer lines, and headwalls. Monument signs and a traffic calming design entrance feature shall be installed at the northerly entrance to the Ridgeview Village Unit 9 subdivision along Beatty Drive.

The work described in the Agreement is anticipated to start in Summer 2022, and onsite improvements are currently underway.

Proposed Resolution for Road Closure
The Agreement requires the Developer to prepare a traffic control plan, and states that no road closure will be permitted without the approval of the Board. The Developer has submitted a request to c...