Title: Department of Transportation recommending the Board: 1) Make findings in accordance with Section 3.13.030 of the County Ordinance that it is more economical and feasible to engage an independent contractor for environmental clearance, permitting services, and construction support services; and 2) Approve and authorize the Chair to sign Second Amendment to Agreement for Services 079-S1711 with Helix Environmental Planning, Inc., who acquired Whitney Environmental Consulting, Inc. dba Foothill Associates, with no other changes to the original agreement and first amendment, which provides continued environmental clearance, permitting services, and construction support services for the El Dorado Trail - Missouri Flat Road to El Dorado Road Project, CIP 97014/36109003, and El Dorado Trail - Missouri Flat Road Bike/Pedestrian Overcrossing Project, CIP 97015/36109002. FUNDING: Accumulative Capital Outlay (<1%), Active Transportation Program (31%), Congestion Mitigation and Air Quality Progr...
Attachments: 1. A - Contract Routing Sheet, 2. B - Agreement for Services #3967, 3. Executed Agreement 3967/079-S1711
Related files: 16-0550
Title
Department of Transportation recommending the Board:
1) Make findings in accordance with Section 3.13.030 of the County Ordinance that it is more economical and feasible to engage an independent contractor for environmental clearance, permitting services, and construction support services; and
2) Approve and authorize the Chair to sign Second Amendment to Agreement for Services 079-S1711 with Helix Environmental Planning, Inc., who acquired Whitney Environmental Consulting, Inc. dba Foothill Associates, with no other changes to the original agreement and first amendment, which provides continued environmental clearance, permitting services, and construction support services for the El Dorado Trail - Missouri Flat Road to El Dorado Road Project, CIP 97014/36109003, and El Dorado Trail - Missouri Flat Road Bike/Pedestrian Overcrossing Project, CIP 97015/36109002.

FUNDING: Accumulative Capital Outlay (<1%), Active Transportation Program (31%), Congestion Mitigation and Air Quality Program (18%), Highway Safety Improvement Program (46%), Air Quality Management District and Air Pollution Control District Grant (4%). (Federal Funds)
Body
DISCUSSION / BACKGROUND
On August 2, 2016, Item 21, Legistar 16-0550, the Department of Transportation (Transportation) brought to the Board for approval Agreement for Services 079-S1711 (Agreement) with Whitney Environmental Consulting, dba Foothill Associates (Foothill), which provides environmental clearance, permitting services, and construction support services for the El Dorado Trail - Missouri Flat Road to El Dorado Road Project and El Dorado Trail - Missouri Flat Road Bike/Pedestrian Overcrossing Project (Projects). First Amendment to Agreement for Services 079-S1711 (Amendment 1) was approved by the Board on December 19, 2017, Item 22, Legistar 16-0550, which provided additional environmental support services, increased the not-to-exceed amount of the contract, and extended the performance period. On April 2, 2019,...