File #: 12-0440    Version: 1
Type: Agenda Item Status: Approved
File created: 4/5/2012 In control: Board of Supervisors
On agenda: 5/8/2012 Final action: 5/8/2012
Title: Department of Transportation recommending the Board authorize the Department to proceed with ordering and payment of title reports to commence the acquisition process for the Alder Drive at EID Canal - Bridge Replacement Project, CIP No. 77123, affecting portions of the following subject parcels: 1) APN 076-132-15, David K. Hutchison and Lana M. Hutchison, Co-Trustees of the David K. and Lana M. Hutchison 2009 Revocable Trust; 2) APN 076-133-12, Barbara Finley, Trustee of the Barbara Finley 2008 Living Revocable Trust; 3) APN 076-133-17, James H. Goodhew and Melva T. Goodhew; 4) APN 076-134-06, Randal J. Long and Debbie Ann Long; 5) APN 076-134-07, Ted A. Morris and Debbie D. Morris; 6) APN 076-230-24, Kuldip Singh and Satkamaljit Birk; and 7) APN 076-230-25, Janice A. Frogner. FUNDING: Highway Bridge Program Grant Funds.
Attachments: 1. A - Vicinity Map
Title
Department of Transportation recommending the Board authorize the Department to proceed with ordering and payment of title reports to commence the acquisition process for the Alder Drive at EID Canal - Bridge Replacement Project, CIP No. 77123, affecting portions of the following subject parcels:
1) APN 076-132-15, David K. Hutchison and Lana M. Hutchison, Co-Trustees of the David K. and Lana M. Hutchison 2009 Revocable Trust;
2) APN 076-133-12, Barbara Finley, Trustee of the Barbara Finley 2008 Living Revocable Trust;
3) APN 076-133-17, James H. Goodhew and Melva T. Goodhew;
4) APN 076-134-06, Randal J. Long and Debbie Ann Long;
5) APN 076-134-07, Ted A. Morris and Debbie D. Morris;
6) APN 076-230-24, Kuldip Singh and Satkamaljit Birk; and
7) APN 076-230-25, Janice A. Frogner.

FUNDING: Highway Bridge Program Grant Funds.
Body
BUDGET SUMMARY:
Total Estimated Cost $3,150

Funding
Budgeted $3,150
New Funding $
Savings $
Other $
Total Funding Available $3,150
Change To Net County Cost $0

Fiscal Impact/Change to Net County Cost:
Funding for this portion of the acquisition process will be provided by Highway Bridge Program grant funds.

Background:
The Alder Drive @ EID Canal - Bridge Replacement Project (Project) is located approximately 2.5 miles southwest of the community of Pollock Pines. The existing bridge is functionally obsolete and does not meet current traffic needs due to its narrow width. The new bridge is proposed to be two lanes to meet current traffic needs and current design standards. Construction is anticipated to begin in spring 2016.

Reason for Recommendation:
The Department of Transportation (Department) was awarded a Highway Bridge Program grant for the Project. The Project is subject to the California Environmental Quality Act (CEQA) and the National Environmental Policy Act (NEPA). The CEQA Mitigated Negative Declaration and the NEPA Finding of No Si...

Click here for full text