Title
Department of Transportation recommending the Board:
1) Authorize the Chair to sign the Easement Acquisition Agreement for Public Purposes and the Certificate of Acceptance for the related documents from Salvador B. Vazquez and Guillermina H. Vazquez, Husband and Wife, As Joint Tenants, as to an Undivided 1/2 Interest and Salvador B. Vazquez and Guillermina H. Vazquez, Husband and Wife, as to an Undivided 1/2 Interest, for Assessor's Parcel Number 036-412-04; and
2) Authorize the Interim Director of Transportation or her designee to execute the escrow instructions and any other related escrow documents pertaining to the transaction, including the payment of title and escrow fees, for the Christmas Valley Phase 2C Erosion Control Project, CIP No. 95190.
FUNDING: California Tahoe Conservancy Grant Funds and Tahoe Regional Planning Agency Mitigation Funds.
Body
BUDGET SUMMARY:
Total Estimated Cost $1,800
Funding
Budgeted $1,800
New Funding $
Savings $
Other $
Total Funding Available $1,800
Change To Net County Cost $0
Fiscal Impact/Change to Net County Cost:
Acquisition costs are $700 with title and escrow fees estimated at $1,100 for a total estimated cost of $1,800. Funding for the acquisition process will be provided by California Tahoe Conservancy grant funds and Tahoe Regional Planning Agency Mitigation Funds.
Background:
The Department of Transportation (Department) is working to advance the Christmas Valley Phase 2C Erosion Control Project (Project), which will design and implement erosion control and water quality improvement measures reducing the discharge of sediment and pollutants into Lake Tahoe. It is anticipated that the Department will begin construction on this Project during the 2012 construction season.
The Project area is located in South Lake Tahoe in the Meyers area, south of Highway 50 and east of Highway 89. The Project is identified in the Tahoe Regiona...
Click here for full text