General Services Director requesting authorization to sign Change Order 01 to Agreement 717-C0899 with Sabah International increasing the contract term by eighty eight (88) calendar days under the authority of the Public Contract Code for the InformationTechnologies Fire Suppression System project.
RECOMMENDED ACTION: Approve.
Body
BUDGET SUMMARY: |
|
|
Total Estimated Cost |
|
$0.00 |
|
|
|
Funding |
|
|
Budgeted |
$ |
|
New Funding |
$ |
|
Savings |
$ |
|
Other |
$ |
|
Total Funding Available |
$ |
|
Change To Net County Cost |
|
$0.00 |
Fiscal Impact/Change to Net County Cost: No Fiscal Impact
Background: General Services entered into Agreement 717-C0899 with Sabah International for the IT Fire Suppression System project on April 7, 2008 with a not to exceed amount of $93,900.00. The original contract term provided for a one hundred and fifty (150) calendar day performance period.
Reason for Recommendation: Due to delays in manufacturing of materials, it is necessary to extend the contract term by eighty eight (88) calendar days.
Action to be taken following Board approval: General Services will complete the administrative process for the Change Order.