File #: 07-672    Version: 1
Type: Agenda Item Status: Approved
File created: 4/18/2007 In control: Board of Supervisors
On agenda: 6/12/2007 Final action: 6/12/2007
Title: Transportation Department recommending the following pertaining to the Euer Ranch, Unit 2 Subdivision (TM96-1317): (1) Accept the subdivision improvements as complete; (2) Reduce Performance Bond No. SU5007984 by $3,421,577.70 to $380,175.30 to guarantee against defective work, labor done, or defective materials furnished and release one year after acceptance if no claims are made; and (3) Hold Laborer and Materialmens Bond No. SU5007984 in the amount of $1,900,876.50 to guarantee payment to persons furnishing labor, materials or equipment and release in six months after acceptance if no claims are made. RECOMMENDED ACTION: Approve.
Attachments: 1. Laborer & Materialmens Bond, 2. Performance Bond, 3. Subd Map, 4. Viciinity Map
Title
Transportation Department recommending the following pertaining to the Euer Ranch, Unit 2 Subdivision (TM96-1317):
(1) Accept the subdivision improvements as complete;
(2) Reduce Performance Bond No. SU5007984 by $3,421,577.70 to $380,175.30 to guarantee against defective work, labor done, or defective materials furnished and release one year after acceptance if no claims are made; and
(3) Hold Laborer and Materialmens Bond No. SU5007984 in the amount of $1,900,876.50 to guarantee payment to persons furnishing labor, materials or equipment and release in six months after acceptance if no claims are made.
RECOMMENDED ACTION: Approve.

Body
BUDGET SUMMARY:
Total Estimated Cost $0

Funding
Budgeted $0
New Funding $0
Savings $0
Other $0
Total Funding Available $0
Change To Net County Cost $0

Fiscal Impact/Change to Net County Cost:

There is no immediate or short-term fiscal impact associated with this action as the roads are private.

Reason for Recommendation:

The Subdivision Improvements for Euer Ranch, Unit 2 have been substantially completed according to the plans, specifications and conditions of the Agreement to Make Subdivision Improvements for Class I Subdivisions Between the County and Owner dated August 31, 2004.

The Performance Bond No. SU5007984 in the amount of $3,801,753.00 is being reduced by $3,421,577.70 to $380,175.30, which is 10% of the total improvements. This amount guarantees against any defective work, labor done or defective materials furnished.

The Laborer and Materialmens Bond No. SU5007984 for $1,900,876.50 guarantees payment to persons furnishing labor, materials or equipment.

Action to be taken following Board approval:

1. The Clerk of the Board will:

a. Reduce the Performance Bond No. SU5007984 to $380,175.30.

b. Hold Laborer and Materialmens Bond No. SU5007984 for $1,900,876.50.

2. The Department will request the Cle...