File #: 24-1550    Version: 1
Type: Agenda Item Status: Approved
File created: 8/26/2024 In control: Board of Supervisors
On agenda: 9/24/2024 Final action: 9/24/2024
Title: Department of Transportation recommending the Board consider the following: 1) Approve and authorize the Chair to sign the Notice of Acceptance with B & M Builders, Inc. for the Intersection Safety / Pedestrian Safety and Sight Triangle Improvement Projects, Capital Improvement Program Numbers 36105061/36105062, Contract 7443; and 2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period. (District 3) FUNDING: Highway Safety Improvement Program - HSIP (40%), Highway Infrastructure Program - HIP (7%) (Federal Funds), RSTP Advance - El Dorado County Transportation Commission - EDCTC (45%), Transportation Development Act - TDA (5%) (State Funds), Tribe (3%) (Local Funds).
Attachments: 1. A - Notice of Acceptance.pdf, 2. Executed Notice of Acceptance
Related files: 23-1260
Title
Department of Transportation recommending the Board consider the following:
1) Approve and authorize the Chair to sign the Notice of Acceptance with B & M Builders, Inc. for the Intersection Safety / Pedestrian Safety and Sight Triangle Improvement Projects, Capital Improvement Program Numbers 36105061/36105062, Contract 7443; and
2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period.
(District 3)

FUNDING: Highway Safety Improvement Program - HSIP (40%), Highway Infrastructure Program - HIP (7%) (Federal Funds), RSTP Advance - El Dorado County Transportation Commission - EDCTC (45%), Transportation Development Act - TDA (5%) (State Funds), Tribe (3%) (Local Funds).
Body
DISCUSSION / BACKGROUND
The Board approved the contract for the Intersection Safety / Pedestrian Safety and Sight Triangle Improvement Projects (Project) on July 25, 2023 (Legistar File 23-1260), at which time the Board also authorized an increase to total project cost due to the receipt of construction bids that were higher than anticipated. Construction started on November 6, 2023, and construction was substantially completed on March 28, 2024. This combined project constructed ADA compliant crosswalks, sidewalks, and pedestrian curb ramps in the towns of El Dorado and Diamond Springs, along with improved sight distance at four (4) intersections of Pleasant Valley Road at Zandonella Road/Big Cut Road, Hanks Exchange Road, Cedar Ravine Road, and Newton Road. Recordation of the Notice of Acceptance (NOA) will start legal time frames for guarantees, a lien period, and return of retention monies. Recordation of the NOA will also start the one-year time frame for releasing the Payment and Performance Bonds to the Surety.

Direct Construction Cost Summary:

Original Bid Price $ 966,990.00
Contract Item Cost $ 911,513.50
Contract Change Orde...