File #: 16-0632    Version:
Type: Agenda Item Status: Approved
File created: 6/3/2016 In control: Board of Supervisors
On agenda: 9/26/2017 Final action: 9/26/2017
Title: Chief Administrative Office, Facilities Division, recommending the Board consider authorizing the Purchasing Agent to sign Amendment II, to Agreement for Services 160-S1610 with Capital Engineering Consultants, Inc. to extend the term one (1) year to provide engineering services as related to the mechanical renovation of the South Lake Tahoe County facility at 1360 Johnson Boulevard, with no change in compensation or scope. FUNDING: Accumulative Capital Outlay Fund.
Attachments: 1. 2A - Amnd II 160-S1610 DRAFT 9-26-17, 2. A - Amnd I 160-S1610 6-28-16, 3. B - Agmt 160-S1610 6-28-16
Title
Chief Administrative Office, Facilities Division, recommending the Board consider authorizing the Purchasing Agent to sign Amendment II, to Agreement for Services 160-S1610 with Capital Engineering Consultants, Inc. to extend the term one (1) year to provide engineering services as related to the mechanical renovation of the South Lake Tahoe County facility at 1360 Johnson Boulevard, with no change in compensation or scope.

FUNDING: Accumulative Capital Outlay Fund.
Body
DEPARTMENT RECOMMENDATION
Chief Administrative Office, Facilities Division, recommending the Board consider authorizing the Purchasing Agent to sign Amendment II, to Agreement for Services 160-S1610 with Capital Engineering Consultants, Inc. to extend the term one (1) year to provide engineering services as related to the mechanical renovation of the South Lake Tahoe County facility at 1360 Johnson Boulevard. There is no change in compensation or scope.

DISCUSSION / BACKGROUND
On October 5th, 2015, the Purchasing Agent executed Agreement for Service No. 160-S1610 with Capital Engineering Consultants, Inc. (Capital) to provide an in-depth analysis of the facility mechanical system. The existing system is upwards of 45 years old, well past its useful life, and maintenance time and costs are exceedingly high. The analysis included various repair options that provided the County information regarding technical challenges, code implications, disruption potential and advantages and disadvantages.

On June 28, 2016, the Board approved Amendment I to this agreement to expand the engineering involved to include bidding and construction phase documentation and increase compensation by $48,800 for an Amended not-to-exceed of $88,800.

Amendment II would extend this agreement an additional year; expiring October 4th, 2018. Additional time is needed due to the complexities involved to ensure this project is completed successfully. There is no change in compensation or scope.

ALTERNATIVE...

Click here for full text