Department of Transportation recommending the Board:
1) Approve and authorize the Chair to sign the Notice of Acceptance with Doug Veerkamp General Engineering Inc., for the 2025 Countywide DOT Maintenance Pavement Rehabilitation Projects, Contract 9299 on Larsen Drive, Barkley Road, Mount Aukum Road, Somerset Loop, Salmon Falls Road, Kekin Street, Wailaki Street, Nahane Drive, Henderson Street, Egret Way, Beaver Bre, East River Park Drive, W River Park Drive, Panorama Drive, and Gillette Drive throughout the County for road repairs in the 2025 construction season; and
2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period.
FUNDING: Road Repair and Rehabilitation Act of 2017 (SB1-RMRA) (100%).
Body
DISCUSSION / BACKGROUND
The contract for the 2025 DOT Maintenance Pavement Rehabilitation Project (Project) was approved by the Board on April 8, 2025 (Legistar file 25-0500). The project provided roadway failure repair to designated pavement sections on Larsen Drive, Barkley Road, Mount Aukum Road, Somerset Loop, Salmon Falls Road, Kekin Street, Wailaki Street, Nahane Drive, Henderson Street, Egret Way, Beaver Bre, East River Park Drive, W River Park Drive, Panorama Drive, and Gillette Drive throughout the County in preparation for surface treatments in the 2025 construction season. All roadway repairs were completed by Doug Veerkamp General Engineering Inc. Recordation of the Notice Of Acceptance (NOA) will start legal time frames for guarantees, a lien period, and return of retention monies. Recordation of the NOA will also start the one-year time frame for releasing the Payment and Performance Bonds to the Surety.
Direct Construction Cost Summary:
Original Bid Price $3,753,516.44
Contract Item Cost $3,830,397.22
Contract Change Order Cost $132,674.00
Total Direct Construction Cost $3,963,071.22
Direct Construc...