Title: Community Development Services, Environmental Management Department, recommending the Board consider the following: 1) Approve and authorize the Chair to execute Contract Change Order No. 1 with Doug Veerkamp General Engineering, Inc., in the amount of $71,768.37 for the Union Mine Disposal Site - 2017 Storm Damage Repair Project, PW 17-31190, Contract 2682, retroactive to work completed between June 19, 2018 through August 31, 2018; 2) Make the following finding to waive the competitive bidding process for the change order: the nature of the subject of the contract is such that competitive proposals would be unavailing or would not produce an advantage, and the advertisement for competitive bids would thus be undesirable, impractical, or impossible; 3) Approve and authorize the Chair to sign the Notice of Acceptance with Doug Veerkamp General Engineering, Inc., for the Union Mine Disposal Site - 2017 Storm Damage Repair Project, PW 17-31190, Contract 2682; and 4) Approve and authori...
Attachments: 1. A - Veerkamp Change Order No. 1, 2. B - Veerkamp Notice of Acceptance, 3. Executed Contract Change Order, 4. Recorded Notice of Acceptance
Related files: 17-0958
Title
Community Development Services, Environmental Management Department, recommending the Board consider the following:
1) Approve and authorize the Chair to execute Contract Change Order No. 1 with Doug Veerkamp General Engineering, Inc., in the amount of $71,768.37 for the Union Mine Disposal Site - 2017 Storm Damage Repair Project, PW 17-31190, Contract 2682, retroactive to work completed between June 19, 2018 through August 31, 2018;
2) Make the following finding to waive the competitive bidding process for the change order: the nature of the subject of the contract is such that competitive proposals would be unavailing or would not produce an advantage, and the advertisement for competitive bids would thus be undesirable, impractical, or impossible;
3) Approve and authorize the Chair to sign the Notice of Acceptance with Doug Veerkamp General Engineering, Inc., for the Union Mine Disposal Site - 2017 Storm Damage Repair Project, PW 17-31190, Contract 2682; and
4) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Environmental Management Department, after the one (1) year guarantee period. (Est. Time: 5: Min)

FUNDING: Non-General Fund / County Service Area No. 10 Funds, with Environmental Management Department staff working with the Federal Emergency Management Agency to obtain emergency reimbursement.


Body
DISCUSSION / BACKGROUND
Beginning in early January 2017, a series of heavy rainstorms over approximately eight (8) weeks severely damaged areas of El Dorado County, including roadways, parks, and areas within the active and inactive portions of the Union Mine Landfill and adjacent support areas of the disposal facility property. The damages caused by the 2017 rainstorms, including the damages to the Union Mine Disposal Site, were presented to the Board on February 27, 2017 (Item 1, File No. 17-0242).

Following the conclusion of the wet weather season, the Environ...