File #: 11-1399    Version:
Type: Agenda Item Status: Approved
File created: 12/2/2011 In control: Board of Supervisors
On agenda: 3/25/2014 Final action: 3/25/2014
Title: Community Development Agency, Environmental Management Division, recommending the Board consider the following: 1) Approve and authorize the Director to sign Amendments to Change Orders 1, 9, 13, 14, 29, and 33 to Public Works Contract No.013-PW-09/10-BOS (138-C1199) with Sukut, Construction, Inc. for a combined reduction of $112,222.62 and reallocate funds to Change Order 36 ($80,222.62) and remaining funds ($32,000) to another contract associated with the Meyers Landfill closure project; 2) Approve and authorize the Director to sign Amendment 2 to Change Order 36 increasing the amount $80,222.62 for a not to exceed amount of $511,413.98 for additional erosion and repair work required post closure but prior to Forest Service certification that the Remedial Action is complete; 3) Approve and authorize the Director to sign Change Order 38 decreasing bid schedule Item No. 7, 20 and 23 in the combined amount of $18,000 and reallocate funds to another contract associated with the Meyers L...
Attachments: 1. 5A - Change Order # 001-2 3-25-14, 2. 5B - Change Order # 009-2 3-25-14, 3. 5C - Change Order # 013-4 3-25-14, 4. 5D - Change order # 014-3 3-25-14, 5. 5E - Change Order # 029-1 3-25-14, 6. 5F - Change Order # 033-2 3-25-14, 7. 5G - Change Order # 036-2 3-25-14, 8. 5H - Change Order # 038 3-25-14, 9. 5I - Change Order Summary 3-25-14, 10. 5K - Affidavit of Payment 3-25-14, 11. 5J - Sukut First Amendment 3-25-14, 12. 5L - Contractor Certification 3-25-14, 13. 5M - Certificate for Payment 3-25-14, 14. 5N - Notice of Acceptance 3-25-14, 15. Executed First Amend. Sukut.pdf, 16. 4A - Sukut Change Order Summary 5-7-13, 17. 4B - Change Order #011-1 5-7-13, 18. 4C - Change Order #012-1 5-7-13, 19. 4D - Change Order #013-3 5-7-13, 20. 4E - Change Order #015-2 5-7-13, 21. 4F - Change Order #022-1 5-7-13, 22. 4G - Change Order #027-1 5-7-13, 23. 4H - Change Order #028-1 5-7-13, 24. 4I - Change Order #030-1 5-7-13, 25. 4J - Change Order #031-1 5-7-13, 26. 4K - Change Order #032-2 5-7-13, 27. 4L - Change Order #033-1 5-7-13, 28. 4M - Change Order #036 5-7-13, 29. 4N - Change Order #037 5-7-13, 30. 3A - Change Order #035, Amend 1, 31. 3B - Change Order #036, 32. 3C - Change Order #013-2, 33. 2A -Change Order 013-1.pdf, 34. 2A2 - Change Order 13-1 Attachment.pdf, 35. 2B - Change Order 014-2.pdf, 36. 2B2 - Change Order 14-2 Attachment.pdf, 37. 2C - Change Order 032-1.pdf, 38. 2D - Change Order 033.pdf, 39. 2E - Change Order 034.pdf, 40. 2F - Change Order 035.pdf, 41. 2G - Blue Route 04.17.12 - Approved.pdf, 42. A - Change Order #009-1.pdf, 43. B - Change Order #014-1.pdf, 44. B1 - Change Order #14-1 Attachment.pdf, 45. C - Change Order #017.pdf, 46. D - Change Order #018.pdf, 47. E - Change Order #019.pdf, 48. F - Change Order #020.pdf, 49. G - Change Order #021.pdf, 50. H - Change Order #022.pdf, 51. I - Change Order #023.pdf, 52. J - Change Order #024.pdf, 53. K - Change Order #025.pdf, 54. L - Change Order #026.pdf, 55. M - Change Order #027.pdf, 56. N - Change Order #028.pdf, 57. O - Change Order #029.pdf, 58. P - Change Order #030.pdf, 59. Q - Change Order #031.pdf, 60. R - Change Order #032, 61. S - Sukut Change Order Summary 12.13.11.pdf
Title
Community Development Agency, Environmental Management Division, recommending the Board consider the following:
1) Approve and authorize the Director to sign Amendments to Change Orders 1, 9, 13, 14, 29, and 33 to Public Works Contract No.013-PW-09/10-BOS (138-C1199) with Sukut, Construction, Inc. for a combined reduction of $112,222.62 and reallocate funds to Change Order 36 ($80,222.62) and remaining funds ($32,000) to another contract associated with the Meyers Landfill closure project;
2) Approve and authorize the Director to sign Amendment 2 to Change Order 36 increasing the amount $80,222.62 for a not to exceed amount of $511,413.98 for additional erosion and repair work required post closure but prior to Forest Service certification that the Remedial Action is complete;
3) Approve and authorize the Director to sign Change Order 38 decreasing bid schedule Item No. 7, 20 and 23 in the combined amount of $18,000 and reallocate funds to another contract associated with the Meyers Landfill closure project resulting in a cumulative net decrease of $50,000 in the total not to exceed amount of $8,136,074.84 with Sukut Construction, Inc, thereby establishing a new not to exceed amount of $8,086,074.84 (see attached Change Order Summary), to be effective March 25, 2014, and in so doing find that it is in the public interest to waive competitive bidding for the work described therein;
4) Approve and Authorize the Chair to sign the First Amendment to the Sukut Construction Agreement (Public Works Contract No. 013 PW 09/10 BOS), Article 6, Final Payment, paragraph one, to omitting, “; and (3) after the Forest Service approves the Completion Report”;
5) Accept the Affidavit of Payment and Contractor Certification submitted by Sukut to the County;
6) Accept the final Certificate for Payment issued by Geosyntec Consultants, Inc., the County’s Construction Quality Assurance Consultant;
7) Approve and authorize the Director to sign the Notice of Completion (Notice of ...

Click here for full text