File #: 07-524    Version: 1
Type: Agenda Item Status: Approved
File created: 3/20/2007 In control: Board of Supervisors
On agenda: 6/5/2007 Final action: 6/5/2007
Title: Transportation Department recommending Chairman be authorized to sign Notice of Completion accepting the Missouri Flat Road/El Dorado Road Signalization Intersection Improvements Project 73125 as substantially complete. RECOMMENDED ACTION: Approve. FUNDING: Hazard Elimination Safety Program (HES Grant), Regional Surface Transportation Program (RSTP) Exchange Funds from the El Dorado County Transportation Commission and the 2004 General Plan Traffic Impact Mitigation (TIM) Fee Program.
Attachments: 1. 73125 Acceptance Statement, 2. 73125 Notice of Completion, 3. 73125 Recording Requested By, 4. 73125 Attachment A, 5. 73125 Location Map
Title
Transportation Department recommending Chairman be authorized to sign Notice of Completion accepting the Missouri Flat Road/El Dorado Road Signalization Intersection Improvements Project 73125 as substantially complete.
RECOMMENDED ACTION: Approve.

FUNDING: Hazard Elimination Safety Program (HES Grant), Regional Surface Transportation Program (RSTP) Exchange Funds from the El Dorado County Transportation Commission and the 2004 General Plan Traffic Impact Mitigation (TIM) Fee Program.
Body
BUDGET SUMMARY:
Total Estimated Cost $0.00

Funding
Budgeted $
New Funding $
Savings $
Other $
Total Funding Available $
Change To Net County Cost $0.00

Fiscal Impact/Change to Net County Cost:
There is no Fiscal Impact associated with this item. There is no cost to the County General Fund.

Reason for Recommendation:
The Contract for the Missouri Flat Road and El Dorado Road Signalization and Intersection Improvements Project (Project) at the intersection of Missouri Flat Road and El Dorado Road was executed by the Board on April 4, 2006. The Project was substantially completed on November 16, 2006. Negotiations between Granite Construction Company and the Department of Transportation regarding cost data for extra work billings has delayed the submittal of extra work bills and subsequently has also delayed the execution of the Final Estimate and the Notice of Completion by several months.

The Board actions above will start legal time frames for guarantees, a lien period, and return of retention monies. Granite Construction Company acceptance of the final Contract cost is attached and summarized below:

Original Bid Price $713,410.76

Construction Contract Item Cost $666,297.08
Contract Change Orders $ 89,032.73
Final Cost of Construction $755,329.81

Major Contract Change Orders on this Project dealt with traffic control, erosion control measures, modification of the ...