File #: 07-529    Version:
Type: Agenda Item Status: Approved
File created: 3/20/2007 In control: Board of Supervisors
On agenda: 6/5/2007 Final action: 6/5/2007
Title: Transportation Department recommending Chairman be authorized to sign Notice of Completion accepting the Missouri Flat Road and Golden Center Drive Traffic Signalization Project 73356 as substantially complete. RECOMMENDED ACTION: Approve. FUNDING: 2004 General Plan Traffic Impact Mitigation (TIM) Fee Program.
Attachments: 1. 73356 Acceptance Statement, 2. 73356 Notice of Completion, 3. 73356 Attachment A, 4. 73356 Recording Request, 5. 73356 Site Map
Title
Transportation Department recommending Chairman be authorized to sign Notice of Completion accepting the Missouri Flat Road and Golden Center Drive Traffic Signalization Project 73356 as substantially complete.
RECOMMENDED ACTION: Approve.

FUNDING: 2004 General Plan Traffic Impact Mitigation (TIM) Fee Program.


Body
BUDGET SUMMARY:
Total Estimated Cost $0.00

Funding
Budgeted $
New Funding $
Savings $
Other $
Total Funding Available $
Change To Net County Cost $0.00

Fiscal Impact/Change to Net County Cost:
There is no Fiscal Impact associated with this item. There is no cost to the County General Fund.

Reason for Recommendation:
The Contract for the Missouri Flat Road and Golden Center Drive Traffic Signalization Project (Project) at the intersection of Missouri Flat Road and Golden Center Drive was executed by the Board on June 27, 2006. The Project was substantially completed November 10, 2006. Negotiations between Richard A. Heaps Electrical Contractors, Inc. and the Department of Transportation regarding cost data for extra work billings has delayed the submittal of extra work bills and subsequently has also delayed the execution of the Final Estimate and the Notice of Completion by several months.

The Board actions above will start legal time frames for guarantees, a lien period, and return of retention monies. Richard A. Heaps Electrical Contractors, Inc. acceptance of the final Contract cost is attached and summarized below:

Original Bid Price $241,600.00

Construction Contract Item Cost $230,165.90
Contract Change Orders $ 12,508.73
Final Cost of Construction $242,674.63

Major Contract Change Orders on this Project dealt with traffic control, installation of Pedestrian Push Buttons, erosion control measures and installation of additional truncated dome mats in the handicap ramps.

Action to be taken following Board approval:
1) The Chairman will sign the N...