File #: 07-1116    Version:
Type: Agenda Item Status: Department Matters
File created: 6/15/2007 In control: Board of Supervisors
On agenda: 1/8/2008 Final action:
Title: General Services Department recommending the Board receive and file status report pertaining to the implementation of a pilot program for skatepark operations.
Attachments: 1. Skatepark Ordinance.pdf, 2. Skatepark management Plan.pdf, 3. email from Jody Gray 7-16-07.pdf, 4. Proposed Management Plan rcvd 8-15-07.pdf, 5. email from Bill MacKay 8-20-07.pdf, 6. Skate park status Memo 11-21-07.pdf
Related files: 09-1491, 09-0960, 08-1471, 08-1218, 08-0723, 08-0727
Title
General Services Department recommending the Board receive and file status report pertaining to the implementation of a pilot program for skatepark operations.











Body


















BUDGET SUMMARY:
Total Estimated Cost $ N/A

Funding
Budgeted $
New Funding $
Savings $
Other $
Total Funding Available $
Change To Net County Cost $ 0

Fiscal Impact/Change to Net County Cost: None

Background: On August 21, 2007, Agenda Item 23, staff presented the Board with three alternatives for the implementation of a Skatepark Management Plan. Staff received direction to return to the Board in three months with a status report regarding the implementation of a pilot program, for skatepark operations, based on Alternative B. Elements of Alternative B included making repairs to the facility and building together with recruiting for an extra help Park Operations Assistant to monitor the facility and collect fees.

Status:

New signs were placed at the facility but stolen within a few days. The signs will not be placed again until a Supervisor is in place, and the signs will be displayed from inside of the building (in the window).

Staff inventoried the facility and noted that the following repairs, which are needed as a result of vandalism, would be necessary in order to implement the management plan:

· Replace air conditioner (window unit)
· Replace section of chain link perimeter fence
· Replace bathroom sink
· Install new locks on building doors
· Hang new drywall throughout the building
· Replace broken glass
· Paint building interior
· Make miscellaneous concrete repairs to park
· Install new signs with hours of operation and rules
· Purchase and install cash register

Staff has estimated the cost for materials to complete the repairs at $1,200. The Rotary Club, who helped build the park, has agreed to assist in funding park improvements. The Rotary club expressed interest in f...

Click here for full text