File #: 07-1243    Version:
Type: Agenda Item Status: Approved
File created: 7/6/2007 In control: Board of Supervisors
On agenda: 8/14/2007 Final action: 8/14/2007
Title: Transportation Department recommending the Board accept the subdivision improvements for Serrano Village J4 as substantially complete; reduce Performance Bond 929347745 by $223,058.61 to $218,896.50 to guarantee against any defective work, labor done or defective materials furnished and release after one year if no claims are made; and hold Laborer and Materialsmen Bond 929347745 in the amount of $1,094,482.50 to guarantee payment to persons furnishing labor, materials or equipment and release after six months if conditions are met. RECOMMENDED ACTION: Approve. FUNDING: Not Applicable.
Attachments: 1. Subd Map, 2. Vicinity Map, 3. Performance Bond, 4. Rider, 5. L & M Bond, 6. General Purpose Rider
Title
Transportation Department recommending the Board accept the subdivision improvements for Serrano Village J4 as substantially complete; reduce Performance Bond 929347745 by $223,058.61 to $218,896.50 to guarantee against any defective work, labor done or defective materials furnished and release after one year if no claims are made; and hold Laborer and Materialsmen Bond 929347745 in the amount of $1,094,482.50 to guarantee payment to persons furnishing labor, materials or equipment and release after six months if conditions are met.
RECOMMENDED ACTION:  Approve.
 
FUNDING:  Not Applicable.  
 
Body
BUDGET SUMMARY:
 
 
Total Estimated Cost
 
$0
 
 
 
     Funding
 
 
          Budgeted
$0
 
          New Funding
$0
 
          Savings
$0
 
          Other
$0
 
     Total Funding Available
$0
 
Change To Net County Cost
 
$0
      
Fiscal Impact/Change to Net County Cost:
 
There is no immediate or short-term fiscal impact associated with action, as the Serrano - El Dorado Owners Association will maintain the roads.  
 
Reason for Recommendation:
 
The Subdivision Improvements for Serrano Village J4 have been substantially completed according to the plans, specifications and conditions of the Agreement to Make Subdivision Improvements to Class I Subdivisions Between the County and Owner dated November 15, 2005.  
 
The Performance Bond No. 929347745 in the amount of $1,827,201.00, which was previously reduced to $441,995.11, is being reduced by $223,058.61 to $218,896.50 which is 10% of the total improvements.  This amount guarantees against any defective work, labor done or defective materials furnished.  
 
The Laborer and Materialmens Bond No. 929347745 for $1,094,482.50, as amended in the August 15, 2005, General Purpose Rider, guarantees payment to persons furnishing labor, materials or equipment.  
 
Action to be taken following Board approval:
 
1)  The Clerk of the Board will:
 
      a.)  Reduce the Performance Bond No. 929347745 to $218,896.50.
 
      b.)  Hold Laborer and Materialmens Bond No. 929347745 for $1,094,482.50.
 
2)  The Department will request the Clerk of the Board release the Performance Bond after one year and the Laborer and Materialmens Bond after six months, if listed conditions are met.  
 
Contact:
 
Richard W. Shepard, P.E.
Director of Transportation
 
Concurrences: