File #: 07-1727    Version: 1
Type: Agenda Item Status: Approved
File created: 10/22/2007 In control: Board of Supervisors
On agenda: 11/27/2007 Final action: 11/27/2007
Title: Transportation Department recommending the following pertaining to Serrano Village J3A, Unit 1 Subdivision: (1) Accept subdivision improvements as complete; (2) Reduce Performance Bond 929374851 by $426,222.58 to $406,405.97 to guarantee against any defective work, labor done or defective materials furnished and release one year after acceptance if no claims are made; and (3) Hold Laborers and Materialmen Bond 929374851 in the amount of $2,032,029.83 to guarantee payment to persons furnishing labor, materials or equipment and release in six months after acceptance if conditions are met. RECOMMENDED ACTION: Approve.
Attachments: 1. 07-2762 Subdivision Map.pdf, 2. 07-2762 Vicinity Map.pdf, 3. 07-2762 Performance Bond.pdf, 4. 07-2762 L & M Bond.pdf
Title
Transportation Department recommending the following pertaining to Serrano Village J3A, Unit 1 Subdivision:
(1) Accept subdivision improvements as complete;
(2) Reduce Performance Bond 929374851 by $426,222.58 to $406,405.97 to guarantee against any defective work, labor done or defective materials furnished and release one year after acceptance if no claims are made; and
(3) Hold Laborers and Materialmen Bond 929374851 in the amount of $2,032,029.83 to guarantee payment to persons furnishing labor, materials or equipment and release in six months after acceptance if conditions are met.
RECOMMENDED ACTION: Approve.
Body
BUDGET SUMMARY:
Total Estimated Cost $0

Funding
Budgeted $0
New Funding $0
Savings $0
Other $0
Total Funding Available $0
Change To Net County Cost $0

Fiscal Impact/Change to Net County Cost:
There is no Fiscal Impact associated with this action, as the Serrano-El Dorado Owners Association will maintain the roads.

Reason for Recommendation:
The Subdivision Improvements in Serrano Village J3A, Unit 1 have been substantially completed according to the plans, specifications and conditions of the Agreement to Make Subdivision Improvements to Class I Subdivisions Between the County and Owner dated February 14, 2006.

The Performance Bond. No. 929374851 in the amount of $2,867,570.86, which was previously reduced to $832,628.55, is being reduced by $426,222.58 to $406,405.97 which is 10% of the total improvements. This amount guarantees against any defective work, labor done or defective materials furnished.

The Laborer and Materialmens Bond No. 929374851 for $2,032,029.83, guarantees payment to persons furnishing labor, materials or equipment.

Action to be taken following Board approval:

1) The Clerk of the Board will:

a.) Reduce the Performance Bond No. 929374851 to $406,405.97.

b.) Hold Laborer and Materialmens Bond No. 929374851for $2,032,029...