File #: 08-0522    Version: 1
Type: Agenda Item Status: Approved
File created: 4/8/2008 In control: Board of Supervisors
On agenda: 5/6/2008 Final action: 5/6/2008
Title: Transportation Department recommending the following pertaining to West Valley, LLC: (1) Accept as complete the traffic signal and road improvements located at White Rock Road and Valley View Parkway; (2) Reduce Performance Bond No. 08821694 by $142,582.50 to $15,842.50 to guarantee against defective work, labor done or defective materials furnished and release after one year if no claims are made; and (3) Hold Payment Bond No. 08821694 in the amount of $79,212.50 to guarantee payment to persons furnishing labor, materials or equipment and release in six months if no claims are made. RECOMMENDED ACTION: Approve.
Attachments: 1. RIA wBonds, 2. Location Map
Title
Transportation Department recommending the following pertaining to West Valley, LLC:
(1) Accept as complete the traffic signal and road improvements located at White Rock Road and Valley View Parkway;
(2) Reduce Performance Bond No. 08821694 by $142,582.50 to $15,842.50 to guarantee against defective work, labor done or defective materials furnished and release after one year if no claims are made; and
(3) Hold Payment Bond No. 08821694 in the amount of $79,212.50 to guarantee payment to persons furnishing labor, materials or equipment and release in six months if no claims are made.
RECOMMENDED ACTION: Approve.
Body
BUDGET SUMMARY:
Total Estimated Cost $

Funding
Budgeted $
New Funding $
Savings $
Other $
Total Funding Available $
Change To Net County Cost $

Fiscal Impact/Change to Net County Cost:
Per Section 16 ACCEPTANCE of Road Improvement Agreement #AGMT 05-807, the County (Board of Supervisors) will accept the traffic signal and road improvements for maintenance upon completion of all the work and fulfillment of the conditions of the Agreement. Long-term there will be some financial impact to the County as future maintenance of the facilities will affect the Department’s budget. Current estimated cost per signal is $5,000.00 annually. There is no cost to the County General Fund.

Background:
The Board of Supervisors approved Road Improvement Agreement #AGMT 05-807, between the County and West Valley, LLC on December 13, 2005.

Reason for Recommendation:
As of March 25, 2008, the road improvements as shown on the improvement plans for White Rock Road at Valley View Parkway (Crain & Associates) have been substantially completed according to the plans specifications for the project, the conditions of the development agreement dated December 13, 2005, and the conditions of the Valley View Specific Plan.

Performance Bond No. 08821694 in the amount of $158,425 is being redu...