Title
Interim General Services Director requesting authorization to sign the Board Change Order 1 to Agreement 584-C0899 with R. T. English Construction Company Inc. increasing the contract amount by $13,591.84 and the contract term by ninety (90) days under the current authority of the Public Contract Code for the Cameron Park Courthouse ADR Modular Building - Sitework project.
RECOMMENDED ACTION: Approve.
Body
BUDGET SUMMARY: |
|
|
Total Estimated Cost |
|
$13,591.84 |
|
|
|
Funding |
|
|
Budgeted |
$13,591.84 |
|
New Funding |
$ |
|
Savings |
$ |
|
Other |
$ |
|
Total Funding Available |
$ |
|
Change To Net County Cost |
|
$13,591.84 |
Fiscal Impact/Change to Net County Cost: Funding is available within the current Capital Improvement Program budget for this project.
Background: The Board awarded the construction contract for the Cameron Park Courthouse ADR Modular Building Sitework project to R. T. English Construction Company Inc. in the amount of $218,709.00 on January 29, 2008, Agenda item #7.
Reason for Recommendation: Key elements of Change Order order #1 include changing size and number of conduits due to gate relocation. Additional paving and concrete work in parking and crosswalk area.
Action to be taken following Board approval: General Services will complete the administrative process of the Change Order.
Contact: Richard Collier, Capital Programs Manager
Concurrences: