File #: 08-1276    Version: 1
Type: Agenda Item Status: Approved
File created: 8/8/2008 In control: Board of Supervisors
On agenda: 8/19/2008 Final action: 8/19/2008
Title: Facilities and Fleet Services Department recommending the Board ratify the Interim Director's signature on Change Order No. 2 to Agreement 395-C0899 with PBM Construction, Inc. increasing contract amount by $8,870.93 under the current authority of the Public Contract Code for the El Dorado Hills Senior Day Care Center remodel project. RECOMMENDED ACTION: Approve.
Attachments: 1. 395-C0899_PBM Construction_CO2.PDF
Title
Facilities and Fleet Services Department recommending the Board ratify the Interim Director's signature on Change Order No. 2 to Agreement 395-C0899 with PBM Construction, Inc. increasing contract amount by $8,870.93 under the current authority of the Public Contract Code for the El Dorado Hills Senior Day Care Center remodel project.
RECOMMENDED ACTION:  Approve.
Body
BUDGET SUMMARY:
 
 
Total Estimated Cost
 
$8,870.93
 
 
 
     Funding
 
 
          Budgeted
$8,870.93
 
          New Funding
$
 
          Savings
$
 
          Other
$
 
     Total Funding Available
$8,870.93
 
Change To Net County Cost
 
$0.00
      
Fiscal Impact/Change to Net County Cost: funding is available within the current Capital Improvements Program budget for this project.
 
Background: The Board awarded the construction contract for the El Dorado Hills Senior Day Care Center remodel project to PBM Construction Inc. in the amount of $255,612.00 on January 8, 2008 Agenda item #11. Change Order #1 to Agreement 395-C0899  was signed by the Interim Director on April 17, 2008 for additional framing, footings and supports necessary for the project.
 
Reason for Recommendation: Key elements of Change Order #2 include labor and materials for painting of the administration walls and ceiling, repair of water damaged and dry rot areas, and excavation, removal and replacement of existing sewer pipe.
 
Action to be taken following Board approval: Facilities and Fleet Services Department will complete the administrative process of the Change Order.
 
Contact: Richard Collier, Capital Programs Manager
 