File #: 08-1279    Version:
Type: Agenda Item Status: Approved
File created: 8/8/2008 In control: Board of Supervisors
On agenda: 9/23/2008 Final action: 9/23/2008
Title: Transportation Department recommending Performance Bond 82044783 in the amount of $2,374,472.51 be reduced to $722,530.33 for West Valley Village Unit 4 Subdivision. (Cont'd 9/16/08, item 25) RECOMMENDED ACTION: Approve. FUNDING: Developer Funds.
Attachments: 1. W Vly Vlg Unit 4, 2. Completion Schedule for Unit 4, 3. Cert Partial Compltn for Bond Reduction - Unit 4, 4. West Valley_Vicinity Map
Title
Transportation Department recommending Performance Bond 82044783 in the amount of $2,374,472.51 be reduced to $722,530.33 for West Valley Village Unit 4 Subdivision. (Cont'd 9/16/08, item 25)
RECOMMENDED ACTION: Approve.

FUNDING: Developer Funds.
Body
BUDGET SUMMARY: N/A
Total Estimated Cost $

Funding
Budgeted $
New Funding $
Savings $
Other $
Total Funding Available $
Change To Net County Cost $

Fiscal Impact/Change to Net County Cost: None.

Background: The Board of Supervisors approved the Final Map and Subdivision Improvements Agreement (SIA) between the County and Landsource Holding Company, LLC, a Delaware limited liability company, on July 10, 2007, with improvements to be completed by July 10, 2009. The total estimated cost for completing the improvements is $2,992,014.69. At the time the SIA was submitted for approval, the majority of the Storm Drainage and Sanitary Sewer Improvements were already completed. The Performance Bond accepted by the Board, therefore, was in the amount of $2,374,472.51.

Reason for Recommendation: Since the filing of the Final Map in 2007, additional work has been completed on the subdivision, and pursuant to the terms of County Code Sections 16-16-040 and 16-16-052, the Owner has requested a reduction in the amount of the posted security. The Department’s Construction Unit staff has inspected the work performed within this subdivision unit and concurs that the amount of work remaining and identified within the attached Certificate of Partial Completion of Subdivision Improvements and Request for Reduction of Subdivision Security for Work Completed fairly represents the value of the remaining work. Therefore, the Department requests that the Performance Bond No. 82044783 be reduced to $772,530.33. Said amount is the balance after $2,219,484.36 (90% of the work completed) is subtracted from $2,992,014.69 (the original total cost of improv...