Title: Chief Administrative Office, Parks Division recommending the Board: 1) Tentatively approve the final draft of the Summer 2017 River Management Plan (Attachment B) which will serve as the Project Description for the preparation of a California Environmental Quality Act (CEQA) Initial Study document; 2) Direct staff to move forward with the Consultant to complete the CEQA process; and 3) Provide direction to staff on Resolution 065-2002 (Attachment D) relating to the River Management Advisory Committee. (Est. Time: 1 Hr.) FUNDING: River fees.
Attachments: 1. A - RMP update memo to BOS 9-26, 2. B - RMP Final Draft Summer 2017, 3. C - Final RMAC RMP Redline comments 9-26-17, 4. D - RMAC Resolution 065-2002 9-26-17, 5. E - Planning and Parks and Rec Commission Ordinance 9-26-17, 6. F - Letter from River Mgmt Adv. Committee (RMAC) 9-26-17, 7. G - River Management Plan Summary 9-26-17 BOS, 8. H - River Management Plan Update 9-26-17, 9. Public Comment Rcvd 9-26-17 BOS 9-27-17, 10. Public Comment Rcvd 9-25-17 BOS 9-26-17, 11. Public Comment Rcvd 9-22-17 BOS 9-26-17, 12. Public Comment Rcvd 9-21-17 BOS 9-26-17
Related files: 18-0182

Title

Chief Administrative Office, Parks Division recommending the Board:

1) Tentatively approve the final draft of the Summer 2017 River Management Plan (Attachment B) which will serve as the Project Description for the preparation of a California Environmental Quality Act (CEQA) Initial Study document;

2) Direct staff to move forward with the Consultant to complete the CEQA process; and

3) Provide direction to staff on Resolution 065-2002 (Attachment D) relating to the River Management Advisory Committee. (Est. Time: 1 Hr.)

 

FUNDING:  River fees.

Body

DEPARTMENT RECOMMENDATION

Chief Administrative Office, Parks Division recommending the Board:

1) Tentatively approve the final draft of the Summer 2017 River Management Plan (RMP) (Attachment B) which will serve as the Project Description for the preparation of a California Environmental Quality Act (CEQA) Initial Study document; and

2) Direct staff to move forward with the Consultant to complete the CEQA process; and

3) Provide direction to staff on Resolution 065-2002 (Attachment D) relating to the River Management Advisory Committee (RMAC).

 

DISCUSSION / BACKGROUND

Please see attached staff report (Attachment A).

 

ALTERNATIVES

1)The Board could direct staff to make additional changes to the RMP and return at a later date for tentative project approval.  This will delay the CEQA process and implementation of an updated plan in time for the next River season.

2) The Board could choose to not make any changes to the existing RMP.  This will result in a plan that contains processes that are no longer relevant, unenforceable by the Parks Division and not aligned with State Parks or Bureau of Land Management policies. 

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

Planning Commission, Department of Planning and Building, Sheriff

 

CAO RECOMMENDATION

It is recommended that the Board approve this item.

 

FINANCIAL IMPACT

There is no financial impact related to moving forward with the CEQA study.  The FY 2017-18 river program budget includes $23,000 in funding for the Consultant to complete the CEQA process.

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

N/A

 

STRATEGIC PLAN COMPONENT

Infrastructure

 

CONTACT

Laura Schwartz