Title: Sheriff’s Office recommending the Board approve and authorize the Chair to continue perpetual agreement 356-O0010 with Global Tower Assets III, LLC with an annual rental increase of 3% and utility charges which result in a total estimated cost of $7,000 for the term November 1, 2017 through October 31, 2018. FUNDING: General Fund.
Attachments: 1. 3A - Sheriff Blue Route Amendment III Global Tower Assets III, LLC 12-8-15, 2. 3B - Sheriff Amend III Global Tower Agreement 12-08-15, 3. Executed Amendment III to 356-O0010 (12/8/15), 4. 2A - Sheriff Global Tower LLC 11-4-14, 5. 2B - Sheriff GTP Blue Route Sheet 11-4-14, 6. 2C - Sheriff GTP Agr Amendment II 11-4-14, 7. A - Sheriff Spectrum Resources Tower LP 5-9-06
Related files: 20-0412, 18-1284, 19-1211, 20-1025

Title

Sheriff’s Office recommending the Board approve and authorize the Chair to continue perpetual agreement 356-O0010 with Global Tower Assets III, LLC with an annual rental increase of 3% and utility charges which result in a total estimated cost of $7,000 for the term November 1, 2017 through October 31, 2018.

 

FUNDING:  General Fund.

Body

DEPARTMENT RECOMMENDATION

The Sheriff's Office is recommending extending the perpetual contract for an additional year.  This will allow the Sheriff's Office to continue its non-exclusive right to install, maintain, operate and remove radio communication equipment on the tower at Genoa Peak in Carson City, Nevada from November 1, 2017 to October 31, 2018 with a 3% increase in compensation and utility charges for an estimated cost of $7,000.

 

DISCUSSION / BACKGROUND

On November 1, 1999, the Board entered into Agreement 356-O0010 with Spectrum Resources Towers, L.P. for non-exclusive rights to install, maintain, operate and remove radio communication equipment and appurtenances on the tower located at Genoa Peak Site in Carson City, Nevada.

 

On May 9, 2006, the Board signed Amendment I to Tower Lease Agreement 356-O0010 with Global Tower LLC, changing the name of the Owner from Spectrum Resources Towers, L.P to Global Tower LLC. 

 

On November 4, 2014 Amendment II was approved, changing the company name to GTP Acquisition Partners III, LLC.

 

On December 8, 2015 Amendment III was signed changing the name to Global Tower Assets III, LLC.

 

The perpetual agreement with Global Tower Assets III, LLC ends on October 31, 2017, and needs to be renewed for another annual term.  The compensation for the agreement increases by 3% each year, and $95 for utilities for an estimated cost of $7,000 from November 1, 2017 to October 31, 2018.

 

ALTERNATIVES

N/A

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

N/A

 

CAO RECOMMENDATION

Approve as recommended.

 

FINANCIAL IMPACT

There is no Net County Cost impact.  The costs have been budgeted in the Sheriff's Fiscal Year 2017/18 budget, and will continue to be budgeted in future years.

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

No follow up action required

 

STRATEGIC PLAN COMPONENT

Public Safety

 

CONTACT

Undersheriff Randy Peshon