File #: 08-1274    Version: 1
Type: Agenda Item Status: Approved
File created: 8/7/2008 In control: Board of Supervisors
On agenda: 11/18/2008 Final action: 11/18/2008
Title: Transportation Department recommending Chairman be authorized to sign Notice of Completion with Sierra Nevada Construction, Inc. for the Latrobe Road Widening Highway 50 to White Rock Road Project (JN 72402). RECOMMENDED ACTION: Approve. FUNDING: 2004 General Plan El Dorado Hills Traffic Impact Mitigation West Valley, LLC prepayment funds. The requested Board action has no associated fiscal impact.
Attachments: 1. Notice of Completion.pdf, 2. Acceptance Statement.pdf, 3. Attachment A.pdf, 4. Recording Requested By, 5. Vicinity Map
Title
Transportation Department recommending Chairman be authorized to sign Notice of Completion with Sierra Nevada Construction, Inc. for the Latrobe Road Widening Highway 50 to White Rock Road Project (JN 72402).
RECOMMENDED ACTION: Approve.

FUNDING: 2004 General Plan El Dorado Hills Traffic Impact Mitigation West Valley, LLC prepayment funds. The requested Board action has no associated fiscal impact.
Body
BUDGET SUMMARY:
Total Estimated Cost $0.00

Funding
Budgeted $
New Funding $
Savings $
Other $
Total Funding Available $
Change To Net County Cost $0.00

Fiscal Impact/Change to Net County Cost:
There is no Fiscal Impact associated with this agenda item. There is no Net County Cost.

Reason for Recommendation:
The Contract for the Latrobe Road Widening HWY 50 to White Rock Road Project (Project) on Latrobe Road from US Highway 50 to White Rock Road in the El Dorado Hills area was executed by the Board on May 22, 2007. The Project was substantially completed on February 4, 2008.

The delay between substantial completion and the execution of Notice of Completion was caused by several factors, including negotiations regarding extra work, late submittal of extra work bills by the contractor, and the mitigation of stop notices submitted by suppliers and subcontractors. Additionally, towards the end of the Project, a new signal pole was damaged by public traffic. Fabrication of the replacement pole took several months.

The Board actions above will start legal time frames for guarantees, a lien period, and return of retention monies. Sierra Nevada Construction, Inc. acceptance of the final Contract cost is attached and summarized below:

Original Bid Price $ 2,307,007.00
Construction Contract Item Cost $ 2,239,704.26
Contract Change Orders $ 224,949.22
Final Cost of Construction $ 2,464,653.48

Major Contract Change Orders on this Project dealt with Board authori...

Click here for full text